A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?
A.
Finish-to-start
B.
Start-to-start
C.
Finish-to-finish
D.
Start-to-finish