Question 227 - PK0-005 discussion
A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the following has the project manager identified?
A.
Technological factors
B.
Poor sample data
C.
Language barriers
D.
Scope creep
Your answer: