Related questions











What business analysis plan defines the process to be followed in managing the solution scope and requirements?

A.
Requirements management plan
A.
Requirements management plan
Answers
B.
Scope management plan
B.
Scope management plan
Answers
C.
Change management plan
C.
Change management plan
Answers
D.
Project management plan
D.
Project management plan
Answers
Suggested answer: A

Which of the following is a narrative description of the work required for the project?

A.
Contract work breakdown structure (CWBS)
A.
Contract work breakdown structure (CWBS)
Answers
B.
Work breakdown structure (WBS)
B.
Work breakdown structure (WBS)
Answers
C.
Contract statement of work (CSOW)
C.
Contract statement of work (CSOW)
Answers
D.
Statement of work (SOW)
D.
Statement of work (SOW)
Answers
Suggested answer: D

The requirements elicitation process requires that the business analyst and team prepare for the requirements elicitation activities. There are three specific inputs that the business analyst will need in preparing for the requirements elicitation.

Which of the following is NOT one of the three inputs the business analyst will use as he prepares for requirements elicitation?

A.
Solution scope
A.
Solution scope
Answers
B.
Change request
B.
Change request
Answers
C.
Business need
C.
Business need
Answers
D.
Stakeholder list
D.
Stakeholder list
Answers
Suggested answer: B

Mark is the business analyst for his organization. He is working with the solution development team and he believes that the team does not want to implement a certain portion of the requirements. The team is expressing the difficulty of the requirements and how it will be extremely challenging to complete. When Mark asks about a similar project that the team completed, they insist that this is a different type of requirements though Mark believes that it is not.

What is the solution development team appearing to do to the requirements?

A.
Change the prioritization of the requirements based on the past project.
A.
Change the prioritization of the requirements based on the past project.
Answers
B.
Change the prioritization of the requirements based on overstated complexity of the project work.
B.
Change the prioritization of the requirements based on overstated complexity of the project work.
Answers
C.
Get the requirements removed from the project scope.
C.
Get the requirements removed from the project scope.
Answers
D.
Have the business analyst report the difficulty of the project work to the project customer.
D.
Have the business analyst report the difficulty of the project work to the project customer.
Answers
Suggested answer: B

You are the business analyst for your organization. You are currently working with Susan on creating a model as part of the specify and model requirements process. Susan doesn't understand why you need a model. You explain to Susan that a model is just a simplified representation of a complex reality that is useful for understanding that reality and making decisions regarding it. In fact, you tell Susan, model can do all of the following except one option.

Choose the option that model cannot do?

A.
Define the resources that will be needed on the project team
A.
Define the resources that will be needed on the project team
Answers
B.
Define boundaries for the business domain
B.
Define boundaries for the business domain
Answers
C.
Describe a situation or problem
C.
Describe a situation or problem
Answers
D.
Describe thought processes and action flows
D.
Describe thought processes and action flows
Answers
Suggested answer: A

Management would like you to front-load the requirements with the most risk requirements.

Why would management prefer the risky requirements first in the prioritization?

A.
So if the risk comes true the project will fail will little investment in the work.
A.
So if the risk comes true the project will fail will little investment in the work.
Answers
B.
So if the risk comes true then the project manager can mitigate the risk event.
B.
So if the risk comes true then the project manager can mitigate the risk event.
Answers
C.
So if the risk comes true they'll receive the reward as soon as possible.
C.
So if the risk comes true they'll receive the reward as soon as possible.
Answers
D.
So if the risk comes true then there's ample time to correct the problem.
D.
So if the risk comes true then there's ample time to correct the problem.
Answers
Suggested answer: A

You are the business analyst for your organization and are working with Sally, a project manager, for your organization. You and Sally are determining the cost of the labor, materials, equipment, and facilities in order to achieve the different solutions that have been proposed for an identified problem.

What is this process called?

A.
Cost budgeting
A.
Cost budgeting
Answers
B.
Expert judgment
B.
Expert judgment
Answers
C.
Rough order of magnitude cost estimating
C.
Rough order of magnitude cost estimating
Answers
D.
Scoping the project costs
D.
Scoping the project costs
Answers
Suggested answer: C

Your organization needs to adapt to the change economy, new technologies, and an increase in competition in order to survive. They've asked you to complete a business analysis approach that will help them change their organizational policies in order to achieve their goals and objectives.

What business analysis technique has this organization asked you to complete?

A.
Focus groups
A.
Focus groups
Answers
B.
Business rules analysis
B.
Business rules analysis
Answers
C.
Brainstorming
C.
Brainstorming
Answers
D.
Root cause analysis
D.
Root cause analysis
Answers
Suggested answer: B

Martha is observing Gary complete several activities as part of her requirements elicitation process. Martha is simply observing the steps Gary takes to complete his work and she is taking notes. In this instance Martha does not ask Gary any questions.

What type of observation technique is Martha completing?

A.
Shadowing
A.
Shadowing
Answers
B.
Active
B.
Active
Answers
C.
Passive
C.
Passive
Answers
D.
Usage consideration
D.
Usage consideration
Answers
Suggested answer: C

You are the business analyst for your organization. You are currently writing the business goals and objectives as part of the elements for the define business process.

Which one of the following statements best describes the business goals and objectives element?

A.
They describe the processes the solution will need to improve for the project to be successf ul.
A.
They describe the processes the solution will need to improve for the project to be successf ul.
Answers
B.
They describe all of the positive benefits in ratio to the risk and costs of the project.
B.
They describe all of the positive benefits in ratio to the risk and costs of the project.
Answers
C.
They describe all of the required work the project will need to complete in order to reach its objectives.
C.
They describe all of the required work the project will need to complete in order to reach its objectives.
Answers
D.
They describe the ends that the organization is seeking to achieve.
D.
They describe the ends that the organization is seeking to achieve.
Answers
Suggested answer: D