ExamGecko
Home / IIBA / CBAP / List of questions
Ask Question

IIBA CBAP Practice Test - Questions Answers, Page 11

List of questions

Question 101

Report Export Collapse

What business analysis plan defines the process to be followed in managing the solution scope and requirements?

Requirements management plan
Requirements management plan
Scope management plan
Scope management plan
Change management plan
Change management plan
Project management plan
Project management plan
Suggested answer: A
asked 18/09/2024
jing xue
43 questions

Question 102

Report Export Collapse

Which of the following is a narrative description of the work required for the project?

Contract work breakdown structure (CWBS)
Contract work breakdown structure (CWBS)
Work breakdown structure (WBS)
Work breakdown structure (WBS)
Contract statement of work (CSOW)
Contract statement of work (CSOW)
Statement of work (SOW)
Statement of work (SOW)
Suggested answer: D
asked 18/09/2024
Brent Varona
28 questions

Question 103

Report Export Collapse

The requirements elicitation process requires that the business analyst and team prepare for the requirements elicitation activities. There are three specific inputs that the business analyst will need in preparing for the requirements elicitation.

Which of the following is NOT one of the three inputs the business analyst will use as he prepares for requirements elicitation?

Solution scope
Solution scope
Change request
Change request
Business need
Business need
Stakeholder list
Stakeholder list
Suggested answer: B
asked 18/09/2024
Mike de Roo
33 questions

Question 104

Report Export Collapse

Mark is the business analyst for his organization. He is working with the solution development team and he believes that the team does not want to implement a certain portion of the requirements. The team is expressing the difficulty of the requirements and how it will be extremely challenging to complete. When Mark asks about a similar project that the team completed, they insist that this is a different type of requirements though Mark believes that it is not.

What is the solution development team appearing to do to the requirements?

Change the prioritization of the requirements based on the past project.
Change the prioritization of the requirements based on the past project.
Change the prioritization of the requirements based on overstated complexity of the project work.
Change the prioritization of the requirements based on overstated complexity of the project work.
Get the requirements removed from the project scope.
Get the requirements removed from the project scope.
Have the business analyst report the difficulty of the project work to the project customer.
Have the business analyst report the difficulty of the project work to the project customer.
Suggested answer: B
asked 18/09/2024
Mustafa BeÅŸparmak
40 questions

Question 105

Report Export Collapse

You are the business analyst for your organization. You are currently working with Susan on creating a model as part of the specify and model requirements process. Susan doesn't understand why you need a model. You explain to Susan that a model is just a simplified representation of a complex reality that is useful for understanding that reality and making decisions regarding it. In fact, you tell Susan, model can do all of the following except one option.

Choose the option that model cannot do?

Define the resources that will be needed on the project team
Define the resources that will be needed on the project team
Define boundaries for the business domain
Define boundaries for the business domain
Describe a situation or problem
Describe a situation or problem
Describe thought processes and action flows
Describe thought processes and action flows
Suggested answer: A
asked 18/09/2024
Robert L Swafford
43 questions

Question 106

Report Export Collapse

Management would like you to front-load the requirements with the most risk requirements.

Why would management prefer the risky requirements first in the prioritization?

So if the risk comes true the project will fail will little investment in the work.
So if the risk comes true the project will fail will little investment in the work.
So if the risk comes true then the project manager can mitigate the risk event.
So if the risk comes true then the project manager can mitigate the risk event.
So if the risk comes true they'll receive the reward as soon as possible.
So if the risk comes true they'll receive the reward as soon as possible.
So if the risk comes true then there's ample time to correct the problem.
So if the risk comes true then there's ample time to correct the problem.
Suggested answer: A
asked 18/09/2024
HWANG SEON TAE
48 questions

Question 107

Report Export Collapse

You are the business analyst for your organization and are working with Sally, a project manager, for your organization. You and Sally are determining the cost of the labor, materials, equipment, and facilities in order to achieve the different solutions that have been proposed for an identified problem.

What is this process called?

Cost budgeting
Cost budgeting
Expert judgment
Expert judgment
Rough order of magnitude cost estimating
Rough order of magnitude cost estimating
Scoping the project costs
Scoping the project costs
Suggested answer: C
asked 18/09/2024
Nathan Phelan
52 questions

Question 108

Report Export Collapse

Your organization needs to adapt to the change economy, new technologies, and an increase in competition in order to survive. They've asked you to complete a business analysis approach that will help them change their organizational policies in order to achieve their goals and objectives.

What business analysis technique has this organization asked you to complete?

Focus groups
Focus groups
Business rules analysis
Business rules analysis
Brainstorming
Brainstorming
Root cause analysis
Root cause analysis
Suggested answer: B
asked 18/09/2024
Zied Nassr
40 questions

Question 109

Report Export Collapse

Martha is observing Gary complete several activities as part of her requirements elicitation process. Martha is simply observing the steps Gary takes to complete his work and she is taking notes. In this instance Martha does not ask Gary any questions.

What type of observation technique is Martha completing?

Shadowing
Shadowing
Active
Active
Passive
Passive
Usage consideration
Usage consideration
Suggested answer: C
asked 18/09/2024
Nick Daniel
41 questions

Question 110

Report Export Collapse

You are the business analyst for your organization. You are currently writing the business goals and objectives as part of the elements for the define business process.

Which one of the following statements best describes the business goals and objectives element?

They describe the processes the solution will need to improve for the project to be successf ul.
They describe the processes the solution will need to improve for the project to be successf ul.
They describe all of the positive benefits in ratio to the risk and costs of the project.
They describe all of the positive benefits in ratio to the risk and costs of the project.
They describe all of the required work the project will need to complete in order to reach its objectives.
They describe all of the required work the project will need to complete in order to reach its objectives.
They describe the ends that the organization is seeking to achieve.
They describe the ends that the organization is seeking to achieve.
Suggested answer: D
asked 18/09/2024
NEXAR DONADIO
36 questions
Total 498 questions
Go to page: of 50
Search

Related questions






The table illustrates the statement of cash flows for a courier company for the last fiscal year. Due to aggressive market competition, the management of the company performed a strategy review and based on their findings and the current market conditions they came up with strategic and tactical changes in order to keep a competitive market position. In order to strengthen customer retention strategies through a new competitive advantage, the company is considering implementing a live parcel tracking system. The added value will be that the customers may determine the exact location of the parcel whether it is in a warehouse, crossing the ocean through an overseas ship, or travelling in a delivery truck at any time. The system tracks the location of the parcel by tracking the vehicle in which it is contained. However, for a group of old delivery trucks, it was noticed that the engine sound and vibration disturbed the tracking signal and caused interruptions. Therefore, the tracking does not perform accurately on these vehicles. Although the majority of management would like to sell these vehicles and replace them with newer ones, the Chief Financial Officer (CFO) was strongly against that approach. The CFO argued that instead of hanging tracking devices on the trucks' body, they can have the truck drivers manually send the truck location from a hand held mobile device every 30 minutes. The company has a total of 134 old delivery trucks that have been in service for 10 years. Each vehicle was bought at a price of $22,000. Depreciation is done using a straight line basis and it is estimated that the vehicle depreciates at $1000 per year. The estimated salvage value per vehicle is about $3,000. Another area of tactical improvement for the courier company is pricing. The management strongly believes that they can start a price war with the most aggressive competitor. Management thinks, with their variable cost of $4 per parcel and fixed cost of $6 per parcel, they can win the market. However, after implementing the tracking solution, fixed cost will jump to $8 per parcel which made management reconsider their options. The competitor has variable costs of $5 per parcel and fixed costs o $7 per parcel. The CFO's resistance to replacing the older vehicles represents which type of cost?