ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers, Page 19

Question list
Search
Search

List of questions

Search

Related questions











A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.

What should the risk manager do in this case?

A.

Document the risk in the risk register for analysis.

A.

Document the risk in the risk register for analysis.

Answers
B.

Document the detailed risk consequences,

B.

Document the detailed risk consequences,

Answers
C.

Immediately start the contracting process.

C.

Immediately start the contracting process.

Answers
D.

Proceed with the quantitative risk analysis.

D.

Proceed with the quantitative risk analysis.

Answers
Suggested answer: A

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

A.

Ensure that all project stakeholders have a copy of and understand the project's risk management plan.

A.

Ensure that all project stakeholders have a copy of and understand the project's risk management plan.

Answers
B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

Answers
C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

Answers
D.

Document the known risk triggers as the identified cost and schedule risks in the risk register.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register.

Answers
Suggested answer: D

A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.

What type of risk response is this?

A.

Transfer

A.

Transfer

Answers
B.

Accept

B.

Accept

Answers
C.

Mitigate

C.

Mitigate

Answers
D.

Avoid

D.

Avoid

Answers
Suggested answer: C

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project's risk management activities? (Choose 3)

A.

By helping to monitor variances and trends frequently throughout the project

A.

By helping to monitor variances and trends frequently throughout the project

Answers
B.

By helping to determine the overall project risks

B.

By helping to determine the overall project risks

Answers
C.

By helping the lessons learned from previous risks to be efficiently utilized

C.

By helping the lessons learned from previous risks to be efficiently utilized

Answers
D.

By helping to update the project scope statement document

D.

By helping to update the project scope statement document

Answers
E.

By helping update the risk register and close out expired risks

E.

By helping update the risk register and close out expired risks

Answers
Suggested answer: A, C, E

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.

What should the risk manager do next?

A.

Assess the risk register to ensure the secondary risks are realistic.

A.

Assess the risk register to ensure the secondary risks are realistic.

Answers
B.

Assess the impact of residual and secondary risks on project objectives.

B.

Assess the impact of residual and secondary risks on project objectives.

Answers
C.

Assess the change log to establish that changes were implemented.

C.

Assess the change log to establish that changes were implemented.

Answers
D.

Assess the stakeholder register to determine the impact of initial risks.

D.

Assess the stakeholder register to determine the impact of initial risks.

Answers
Suggested answer: B

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

A.

Develop checklists based on historical information

A.

Develop checklists based on historical information

Answers
B.

Conduct interviews, meetings, and focus groups

B.

Conduct interviews, meetings, and focus groups

Answers
C.

Assign a different risk manager for each portfolio unit

C.

Assign a different risk manager for each portfolio unit

Answers
D.

Employ brainstorming to generate spontaneous ideas

D.

Employ brainstorming to generate spontaneous ideas

Answers
E.

Perform qualitative and quantitative risk analyses

E.

Perform qualitative and quantitative risk analyses

Answers
Suggested answer: A, B, D

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.

What type of request is the risk manager describing?

A.

A request to increase project earnings

A.

A request to increase project earnings

Answers
B.

A request to increase project resources

B.

A request to increase project resources

Answers
C.

A challenge to stakeholder thresholds

C.

A challenge to stakeholder thresholds

Answers
D.

A challenge to the project investment

D.

A challenge to the project investment

Answers
Suggested answer: C

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?

A.

Scenario-based risk analysis

A.

Scenario-based risk analysis

Answers
B.

Quantitative risk analysis

B.

Quantitative risk analysis

Answers
C.

Qualitative risk analysis

C.

Qualitative risk analysis

Answers
D.

Monte Carlo analysis

D.

Monte Carlo analysis

Answers
Suggested answer: C

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

Answers
B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

Answers
C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

Answers
D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted.

D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted.

Answers
Suggested answer: D

An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource's availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.

What should the risk manager do next?

A.

Update the risk register to indicate the risk has occurred and close out the expired risk from the register.

A.

Update the risk register to indicate the risk has occurred and close out the expired risk from the register.

Answers
B.

Update, continuously monitor, and communicate the residual and secondary risks of the backup resource on the project.

B.

Update, continuously monitor, and communicate the residual and secondary risks of the backup resource on the project.

Answers
C.

Hire a permanent developer to support the project, and work with the backup resource to eliminate this risk.

C.

Hire a permanent developer to support the project, and work with the backup resource to eliminate this risk.

Answers
D.

Hire another developer to support the project, contingent on when the experienced developer returns.

D.

Hire another developer to support the project, contingent on when the experienced developer returns.

Answers
Suggested answer: B
Total 201 questions
Go to page: of 21