PMI PMI-RMP Practice Test - Questions Answers, Page 19
List of questions
Question 181

A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.
What should the risk manager do in this case?
Question 182

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.
What should the risk manager do to mitigate the chance of the same issues reoccurring?
Question 183

A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.
What type of risk response is this?
Question 184

In a highly dynamic project environment, the project manager is known to have project risks as a permanent agenda item in their periodic project progress meetings. How will this help improve the project's risk management activities? (Choose 3)
Question 185

A project team has completed plan risk response activities and has identified three critical risk response plans to major risk events. The responses have been monitored and implemented, with one of the responses presenting the two secondary risks.
What should the risk manager do next?
Question 186

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.
What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)
Question 187

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.
What type of request is the risk manager describing?
Question 188

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:
1 = Very Low
2 = Low
3 = Medium
4 = High
5 = Very High
What type of risk analysis is the risk manager performing?
Question 189

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.
How should the risk manager improve collaboration during risk planning?
Question 190

An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource's availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.
What should the risk manager do next?
Question