PMI PMI-RMP Practice Test - Questions Answers, Page 21
Related questions
A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.
Which analysis should the risk manager do to provide the project manager with the performance report?
A.
Time Series Analysis
B.
Regression Analysis
C.
Variance Analysis
D.
Monte Carlo Analysis
Question