Question 201

Report Export Collapse

A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.

Which analysis should the risk manager do to provide the project manager with the performance report?

Become a Premium Member for full access
  Unlock Premium Member

Question 202

Report Export Collapse

When should the benefits of quantitative risk analysis be weighed against the effort required to ensure that the additional insights and value justify the extra effort?

Become a Premium Member for full access
  Unlock Premium Member

Question 203

Report Export Collapse

Some engineers are completing an activity that will alert the project team if there is a risk of requiring additional effort to complete the project. What should the risk manager do in case the trigger arises?

Become a Premium Member for full access
  Unlock Premium Member

Question 204

Report Export Collapse

A key hardware component failed during a large software implementation project with significant organizational impact. The risk owner was on vacation and no one responded to this incident thereby causing project delays.

What should have been done to prevent this situation?

Become a Premium Member for full access
  Unlock Premium Member

Question 205

Report Export Collapse

A team of experts is working on a complex project. Which three tools could support the risk manager in discovering the overall project risk complexity? (Choose 3)

Become a Premium Member for full access
  Unlock Premium Member

Question 206

Report Export Collapse

A stakeholder is asking a project team to hire an external vendor with more expertise and capacity to accelerate a delivery plan. The team has some concerns about this request.

What should the risk manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 207

Report Export Collapse

A company has implemented a policy requirement for employees to use complex passwords and update them regularly. A few employees are unable to make the changes, which increases the likelihood of cybercrimmals compromising their passwords.

What should the risk manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 208

Report Export Collapse

In a complex and critical project, a sponsor asks the risk manager to determine where the project's concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories.

Which tool could the risk manager use to discover the project risk categories?

Become a Premium Member for full access
  Unlock Premium Member

Question 209

Report Export Collapse

It typically takes 5 hours to perform a complete home inspection. It there are unforeseen risk factors. It can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.

Using the project evaluation and review technique (PERT) to estimate duration, how many hours should the project manager plan to schedule the task, taking into account all the positive and negative risk factors?

Become a Premium Member for full access
  Unlock Premium Member

Question 210

Report Export Collapse

During a virtual workshop presenting a product to potential clients, a facilitator emails the product brochure and asks attendees to check their spam folder if the email does not appear in their inbox. What kind of threat strategy is the facilitator applying?

Become a Premium Member for full access
  Unlock Premium Member
Total 273 questions
Go to page: of 28
Search

Related questions