ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers, Page 21

Question list
Search
Search

Related questions











A project is in the execution phase and involves large volumes of supplies. The project is the last phase of a 10-year initiative. The project sponsor asks the project manager to provide the performance report for the whole initiative.

Which analysis should the risk manager do to provide the project manager with the performance report?

A.

Time Series Analysis

A.

Time Series Analysis

Answers
B.

Regression Analysis

B.

Regression Analysis

Answers
C.

Variance Analysis

C.

Variance Analysis

Answers
D.

Monte Carlo Analysis

D.

Monte Carlo Analysis

Answers
Suggested answer: C
Total 201 questions
Go to page: of 21