PMI PMI-RMP Practice Test - Questions Answers, Page 23
List of questions
Question 221

A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded
Which analysis should the risk manager perform to demonstrate this to the stakeholders?
Question 222

During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of USS800.000. Which approach should the risk manager suggest the project manager take?
Question 223

A project team has failed to complete an important project milestone on time. The team was counting on an external provider to deliver key equipment on a specific date but the provider was delayed
What could the risk manager have done to prevent missing the milestone?
Question 224

During a project team meeting, a risk manager realizes that the initial assumptions on the project schedule are too optimistic. The risk manager believes that the project might not meet its deadline as initially stated.
What is the reason for misunderstanding the assumptions from the beginning?
Question 225

After a rigorous risk identification process in a program consisting of three component projects a program management team documented 120 risks in the program risk register. The risk manager is interested in knowing the probability and impact of the occurrence of each identified risk.
What should the risk manager perform?
Question 226

A project is in progress when the product team requests a change to the scope. The learn indicates that this is a minimal change and should not create any problems. What should the risk manager do next?
Question 227

During a risk identification workshop some stakeholders indicate 'lack of procedure' or 'unqualified staff' as risks. The risk manager stops the identification session and coaches about defining a risk.
What represents 'lack of procedure' or 'unqualified staff when identifying risks?
Question 228

The risk manager needs to achieve consensus during the risk planning phase of a construction project that is crucial to an organization's growth. What should the risk manager do to begin the process of identifying risks?
Question 229

A project is delayed and the risk manager is working on a new plan for the remaining work Based on previous results the project team is having frequent issues with quality due to lack of experience in the technology used, requiring additional testing effort and rework.
How should the risk manager and team respond to this type of risk in the future?
Question 230

A project team identified and analyzed known risks at the beginning of a project What should the risk manager do next in relation to the accepted passive risks?
Question