ExamGecko
Home / PMI / PMI-RMP / List of questions
Ask Question

PMI PMI-RMP Practice Test - Questions Answers, Page 23

List of questions

Question 221

Report Export Collapse

A project team does not understand why a very low probability risk occurred during project execution. The team was especially vigilant about planning for this type of risk during the risk planning phase The project has been delayed by 2 months, and the stakeholders are considering canceling the project. The risk manager needs to demonstrate that the project can be concluded

Which analysis should the risk manager perform to demonstrate this to the stakeholders?

Become a Premium Member for full access
  Unlock Premium Member

Question 222

Report Export Collapse

During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of USS800.000. Which approach should the risk manager suggest the project manager take?

Become a Premium Member for full access
  Unlock Premium Member

Question 223

Report Export Collapse

A project team has failed to complete an important project milestone on time. The team was counting on an external provider to deliver key equipment on a specific date but the provider was delayed

What could the risk manager have done to prevent missing the milestone?

Become a Premium Member for full access
  Unlock Premium Member

Question 224

Report Export Collapse

During a project team meeting, a risk manager realizes that the initial assumptions on the project schedule are too optimistic. The risk manager believes that the project might not meet its deadline as initially stated.

What is the reason for misunderstanding the assumptions from the beginning?

Become a Premium Member for full access
  Unlock Premium Member

Question 225

Report Export Collapse

After a rigorous risk identification process in a program consisting of three component projects a program management team documented 120 risks in the program risk register. The risk manager is interested in knowing the probability and impact of the occurrence of each identified risk.

What should the risk manager perform?

Become a Premium Member for full access
  Unlock Premium Member

Question 226

Report Export Collapse

A project is in progress when the product team requests a change to the scope. The learn indicates that this is a minimal change and should not create any problems. What should the risk manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 227

Report Export Collapse

During a risk identification workshop some stakeholders indicate 'lack of procedure' or 'unqualified staff' as risks. The risk manager stops the identification session and coaches about defining a risk.

What represents 'lack of procedure' or 'unqualified staff when identifying risks?

Become a Premium Member for full access
  Unlock Premium Member

Question 228

Report Export Collapse

The risk manager needs to achieve consensus during the risk planning phase of a construction project that is crucial to an organization's growth. What should the risk manager do to begin the process of identifying risks?

Become a Premium Member for full access
  Unlock Premium Member

Question 229

Report Export Collapse

A project is delayed and the risk manager is working on a new plan for the remaining work Based on previous results the project team is having frequent issues with quality due to lack of experience in the technology used, requiring additional testing effort and rework.

How should the risk manager and team respond to this type of risk in the future?

Become a Premium Member for full access
  Unlock Premium Member

Question 230

Report Export Collapse

A project team identified and analyzed known risks at the beginning of a project What should the risk manager do next in relation to the accepted passive risks?

Become a Premium Member for full access
  Unlock Premium Member
Total 273 questions
Go to page: of 28
Search

Related questions