PMI PMI-RMP Practice Test - Questions Answers, Page 27
List of questions
Question 261

A risk manager had to mitigate delay risks in the delivery of a component in a manufacturing project by procuring from an alternate vendor with shorter lead times. This has led to another risk because the project team may need additional training on how to install this specific component.
What should the risk manager do?
Question 262

A risk manager has recommended an increase of 7% to the risk threshold to avoid failure of a challenging new initiative. What should the risk manager do next?
Question 263

When performing a risk analysis, a risk manager identifies not only negative risks but also positive risks, which might bring added value to the project. What should the risk manager do next?
Question 264

The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identity the risks that could affect the project. The team did manage the risks however, some of the risk response strategies created secondary risks.
What should the risk management team have done to manage this situation?
Question 265

During project implementation, a risk manager wants to determine the effectiveness of risk response plans and which risk will have an impact on the project outcome. Which analysis should the risk manager do?
Question 266

A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?
Question 267

A risk manager schedules workshops for identifying risks about an initiative involving multiple business units, recruitments for different roles, procurements, technological uplift training, and changes in the ways of working Who should participate in the risk management activity?
Question 268

A project has suffered a big schedule delay and there are still some risks that are close to materializing. The project manager is concerned about communicating this risk level because the stakeholders might suspend project funding and cancel the project.
How should the risk manager manage the risk level?
Question 269

A financial institution is creating a new product database for their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place.
What type of risk is being referred to here?
Question 270

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed
Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?
Question