During the implementation of a story, a scrum team notifies the scrum master of a technical challenge that is causing a delay. What should the scrum master advise the team lo do?

A.
Implement the story since the team is running behind schedule.
Answers
A.
Implement the story since the team is running behind schedule.
B.
Create a spike to finalize the story's technical approach.
Answers
B.
Create a spike to finalize the story's technical approach.
C.
Transfer the story to a scrum team experienced in solving similar problems.
Answers
C.
Transfer the story to a scrum team experienced in solving similar problems.
D.
Ask the product owner to reduce the story's priority and wait until more technical details are available.
Answers
D.
Ask the product owner to reduce the story's priority and wait until more technical details are available.
Suggested answer: D