Refer to the exhibit.

Refer to the exhibit. A functioning trunk port Ethernet1/48 exists between two identical Cisco Nexus 5000 Series Switches. The interfaces on the switches support the MACsec feature and are configured identically. To enable manual

MACsec, an engineer adds the configuration shown in the exhibit to both sides of the trunk. The trunk port stops functioning. Which action should be taken to resolve the issue?

A.

Disable and then enable the port

A.

Disable and then enable the port

Answers
B.

Enable the license for the trunk ports to support MACsec

B.

Enable the license for the trunk ports to support MACsec

Answers
C.

Lower the MTU value to less than 9216 bytes

C.

Lower the MTU value to less than 9216 bytes

Answers
D.

Configure the PMK with a length of 2048 bytes

D.

Configure the PMK with a length of 2048 bytes

Answers
Suggested answer: B

Refer to the exhibit.

Refer to the exhibit. A network engineer is troubleshooting a Cisco Nexus 5000 Series Switch. The interface between the server and the switch is nonoperational and is expected to operate at 10 Gbps. The drain rate of the interface is 3 Mbps. Which action resolves the issue?

A.

Configure pause error-disable recovery

A.

Configure pause error-disable recovery

Answers
B.

Enable link level pause on the interface

B.

Enable link level pause on the interface

Answers
C.

Reset priority flow counters

C.

Reset priority flow counters

Answers
D.

Set priority flow control pause

D.

Set priority flow control pause

Answers
Suggested answer: A

Explanation:

Reference:

https://www.cisco.com/c/en/us/td/docs/switches/datacenter/nexus5000/sw/troubleshooting/guide/N5K_Troubleshooting_Guide/n5K_ts_fcoe.html

Refer to the exhibit.

A customer network uses OSPFv2 and MP-BGP protocols A network administrator installs a new Cisco Nexus Switch in the data center but experiences a BGP RIB failure Which action solves the issue?

A.

Change the administrative distance of OSPF to 220

A.

Change the administrative distance of OSPF to 220

Answers
B.

Configure the route as a BGP backdoor

B.

Configure the route as a BGP backdoor

Answers
C.

Use a filter list for OSPF to filter both routes

C.

Use a filter list for OSPF to filter both routes

Answers
D.

Implement next-hop-self

D.

Implement next-hop-self

Answers
Suggested answer: A

An engineer is implementing a new BGP peering in their new data center. The engineer set up the BGP session that peers with the remote end. As soon as the BGP peers attempt to exchange routing prefixes, one of the BGP peers drops the connection. After reviewing the configuration, the engineer reviews the logging messages. The engineer discovers that the router is missing keepalives from the remote end and terminates the session. Which action resolves the issue?

A.

Set the bgp transport path-mtu-discovery attribute on both peers

A.

Set the bgp transport path-mtu-discovery attribute on both peers

Answers
B.

Set the higher values for the BGP keepalive and hold-down timers on both peers

B.

Set the higher values for the BGP keepalive and hold-down timers on both peers

Answers
C.

Configure the matching BGP AS numbers between the peers

C.

Configure the matching BGP AS numbers between the peers

Answers
D.

Configure the matching BGP passwords between the peers

D.

Configure the matching BGP passwords between the peers

Answers
Suggested answer: B

Refer to the exhibit.

The vPC neighborship between two switches is in suspended state. Which configuration change resolves the issue and brings up the vPC neighborship?

A.

Change STP Port Type to Network on the peer switch

A.

Change STP Port Type to Network on the peer switch

Answers
B.

Enable Bridge Assurance on the local switches

B.

Enable Bridge Assurance on the local switches

Answers
C.

Configure QoS MTU value of 9216 on the peer switch

C.

Configure QoS MTU value of 9216 on the peer switch

Answers
D.

Add VLAN 400-401 to the configuration on the local switch

D.

Add VLAN 400-401 to the configuration on the local switch

Answers
Suggested answer: C

Explanation:

Reference:

https://www.cisco.com/c/en/us/td/docs/switches/datacenter/nexus5000/sw/troubleshooting/guide/N5K_Troubleshooting_Guide/n5K_ts_vpc.pdf

Refer to the exhibit.

The integration between Cisco UCS Manager and Cisco UCS Central failed. Which action resolves the issue?

A.

Implement the consistent NTP source between the appliances

A.

Implement the consistent NTP source between the appliances

Answers
B.

Implement the connectivity between the appliances through a firewall

B.

Implement the connectivity between the appliances through a firewall

Answers
C.

Configure the certificate between the appliances

C.

Configure the certificate between the appliances

Answers
D.

Configure the shared secret key between the appliances

D.

Configure the shared secret key between the appliances

Answers
Suggested answer: A

Refer to the exhibit.

An engineer fails to implement a Cisco UCS Manager integration manager. The credentials and IP connectivity between Cisco APIC and UCS Manager are configured as expected. Which action resolves the issue?

A.

Disable HTTP to HTTPS redirection in Cisco UCS Manager

A.

Disable HTTP to HTTPS redirection in Cisco UCS Manager

Answers
B.

Enable JSON API on the Cisco UCS Manager

B.

Enable JSON API on the Cisco UCS Manager

Answers
C.

Change the Integration Manager name to FQDN of the Cisco UCS Manager

C.

Change the Integration Manager name to FQDN of the Cisco UCS Manager

Answers
D.

Install ExternalSwitch app in the APIC controller

D.

Install ExternalSwitch app in the APIC controller

Answers
Suggested answer: D

Explanation:

Reference: https://www.cisco.com/c/en/us/td/docs/switches/datacenter/aci/apic/sw/4-x/virtualization/Cisco-ACI-Virtualization-Guide-411/Cisco-ACI-Virtualization-Guide-411_chapter_01110.html

A network engineer experiences the error “DDR3_P1_B1_ECC” when upgrading Cisco UCS firmware.

Which action resolves the issue?

A.

Reset the DIMM

A.

Reset the DIMM

Answers
B.

Reset the BMC firmware

B.

Reset the BMC firmware

Answers
C.

Reflash the controller firmware

C.

Reflash the controller firmware

Answers
D.

Reflash the DIMM

D.

Reflash the DIMM

Answers
Suggested answer: A

Refer to the exhibit.

A Cisco UCS Fabric Interconnect fails during the upgrade process. The working images of the fabric interconnect are stored on the bootflash. Which set of commands recovers the fabric interconnect?

A. loader> dir

loader> boot ucs-6300-k9-kickstart.5.0.2.N1.3.02d56.bin

switch(boot)# init system

switch(boot)# reload

switch(boot)# load ucs-6300-k9-system.5.0.2.N1.3.02d56.bin

A.

loader> dir

loader> boot ucs-6300-k9-kickstart.5.0.2.N1.3.02d56.bin

switch(boot)# copy ics-manager-k9.1.4.1k.bin nuova-sim-mgmt-nsg.0.1.001.bin

switch(boot)# boot ucs-6300-k9-system.5.0.2.N1.3.02d56.bin

A.

loader> dir

loader> boot ucs-6300-k9-kickstart.5.0.2.N1.3.02d56.bin

switch(boot)# copy ics-manager-k9.1.4.1k.bin nuova-sim-mgmt-nsg.0.1.001.bin

switch(boot)# boot ucs-6300-k9-system.5.0.2.N1.3.02d56.bin

Answers
B.

loader> dir

loader> boot ucs-6300-k9-kickstart.5.0.2.N1.3.02d56.bin

switch(boot)# init system

switch(boot)# reload

switch(boot)# boot ucs-6300-k9-system.5.0.2.N1.3.02d56.bin

B.

loader> dir

loader> boot ucs-6300-k9-kickstart.5.0.2.N1.3.02d56.bin

switch(boot)# init system

switch(boot)# reload

switch(boot)# boot ucs-6300-k9-system.5.0.2.N1.3.02d56.bin

Answers
C.

loader> dir

loader> boot ucs-6300-k9-kickstart.5.0.2.N1.3.02d56.bin

switch(boot)# copy ics-manager-k9.1.4.1k.bin nuova-sim-mgmt-nsg.0.1.001.bin

switch(boot)# load ucs-6300-k9-system.5.0.2.N1.3.02d56.bin

C.

loader> dir

loader> boot ucs-6300-k9-kickstart.5.0.2.N1.3.02d56.bin

switch(boot)# copy ics-manager-k9.1.4.1k.bin nuova-sim-mgmt-nsg.0.1.001.bin

switch(boot)# load ucs-6300-k9-system.5.0.2.N1.3.02d56.bin

Answers
Suggested answer:

Refer to the exhibit.

An engineer monitors a Cisco UCS server logs and discovers a blade discovery issue. Which procedure resolves the issue?

A. 1. Verify the server power module.

A.

Decommission the faulty module.

A.

Decommission the faulty module.

Answers
B.

Insert a new power module.

B.

Insert a new power module.

Answers
C.

Recommission the new module.

C.

Recommission the new module.

Answers
D.

1. Verify that server platform power is failed

D.

1. Verify that server platform power is failed

Answers
E.

Resolve the platform power issue.

E.

Resolve the platform power issue.

Answers
F.

Reboot the server.

F.

Reboot the server.

Answers
G.

Recommission the server.

G.

Recommission the server.

Answers
H.

1. Verify the FSM status on the server.

H.

1. Verify the FSM status on the server.

Answers
I.

Decommission the impacted server.

I.

Decommission the impacted server.

Answers
J.

Reset the slot where the server is located.

J.

Reset the slot where the server is located.

Answers
K.

Recommission the server.

K.

Recommission the server.

Answers
L.

1. Verify that the power on self-test operation is failed.

L.

1. Verify that the power on self-test operation is failed.

Answers
M.

Verify that the server firmware is corrupted.

M.

Verify that the server firmware is corrupted.

Answers
N.

Decommission the server firmware

4. Recommission the server with new firmware.

N.

Decommission the server firmware

4. Recommission the server with new firmware.

Answers
Suggested answer: C

Explanation:

Reference: https://www.cisco.com/c/en/us/support/docs/servers-unified-computing/unifiedcomputing-system/214047-troubleshooting-ucs-blade-discovery-issu.pdf

Total 166 questions