The table illustrates the statement of cash flows for a courier company for the last fiscal year. Due to aggressive market competition, the management of the company performed a strategy review and based on their findings and the current market conditions they came up with strategic and tactical changes in order to keep a competitive market position. In order to strengthen customer retention strategies through a new competitive advantage, the company is considering implementing a live parcel tracking system. The added value will be that the customers may determine the exact location of the parcel whether it is in a warehouse, crossing the ocean through an overseas ship, or travelling in a delivery truck at any time. The system tracks the location of the parcel by tracking the vehicle in which it is contained. However, for a group of old delivery trucks, it was noticed that the engine sound and vibration disturbed the tracking signal and caused interruptions. Therefore, the tracking does not perform accurately on these vehicles. Although the majority of management would like to sell these vehicles and replace them with newer ones, the Chief Financial Officer (CFO) was strongly against that approach. The CFO argued that instead of hanging tracking devices on the trucks' body, they can have the truck drivers manually send the truck location from a hand held mobile device every 30 minutes. The company has a total of 134 old delivery trucks that have been in service for 10 years. Each vehicle was bought at a price of $22,000. Depreciation is done using a straight line basis and it is estimated that the vehicle depreciates at $1000 per year. The estimated salvage value per vehicle is about $3,000. Another area of tactical improvement for the courier company is pricing. The management strongly believes that they can start a price war with the most aggressive competitor. Management thinks, with their variable cost of $4 per parcel and fixed cost of $6 per parcel, they can win the market. However, after implementing the tracking solution, fixed cost will jump to $8 per parcel which made management reconsider their options. The competitor has variable costs of $5 per parcel and fixed costs o $7 per parcel. The CFO's resistance to replacing the older vehicles represents which type of cost?





Question 221

Report
Export
Collapse

Which of the following graphical presentations of a project plan is most appropriate for presenting to upper management?

A.
Pie chart
A.
Pie chart
Answers
B.
Pareto Chat
B.
Pareto Chat
Answers
C.
Critical Path Method
C.
Critical Path Method
Answers
D.
Scatter chart
D.
Scatter chart
Answers
Suggested answer: C
asked 18/09/2024
AshokBabu Kumili
43 questions

Question 222

Report
Export
Collapse

Which of the following diagrams is used to display sensitivity analysis data?

A.
Decision tree
A.
Decision tree
Answers
B.
Ishikawa
B.
Ishikawa
Answers
C.
Influence
C.
Influence
Answers
D.
Tornado
D.
Tornado
Answers
Suggested answer: D
asked 18/09/2024
Loyston Mathias
41 questions

Question 223

Report
Export
Collapse

Which of the following is a visual decomposition of the project scope?

A.
Budgeted Cost of Work Scheduled (BCWS)
A.
Budgeted Cost of Work Scheduled (BCWS)
Answers
B.
Resource Breakdown Structure (RBS)
B.
Resource Breakdown Structure (RBS)
Answers
C.
product breakdown structure (PBS)
C.
product breakdown structure (PBS)
Answers
D.
Work Breakdown Structure (WBS)
D.
Work Breakdown Structure (WBS)
Answers
Suggested answer: D
asked 18/09/2024
Danish Vohra
38 questions

Question 224

Report
Export
Collapse

________ are timeless events that show progress in the project.

These are typically achieved at the end of phase in the project lifecycle.

A.
Achievements
A.
Achievements
Answers
B.
Millstones
B.
Millstones
Answers
C.
Phases
C.
Phases
Answers
D.
Templates
D.
Templates
Answers
Suggested answer: B
asked 18/09/2024
KOSSIBA LANTONKPODE
28 questions

Question 225

Report
Export
Collapse

Which of the following authorizes the project to exist within the organization?

A.
Project charter
A.
Project charter
Answers
B.
Project network diagram
B.
Project network diagram
Answers
C.
Project integration management
C.
Project integration management
Answers
D.
Project boundaries
D.
Project boundaries
Answers
Suggested answer: A
asked 18/09/2024
Ian Lloyd
36 questions

Question 226

Report
Export
Collapse

Which of the following tasks cannot start until other tasks are completed?

A.
Analysis task
A.
Analysis task
Answers
B.
Dependent task
B.
Dependent task
Answers
C.
Predecessor task
C.
Predecessor task
Answers
D.
Independent task
D.
Independent task
Answers
Suggested answer: B
asked 18/09/2024
M Kumar
40 questions

Question 227

Report
Export
Collapse

Which of the following roles approves the project scope statement, phase gate reviews, solution validations, scope changes, and project success criteria?

A.
Project manager
A.
Project manager
Answers
B.
Subject matter expert
B.
Subject matter expert
Answers
C.
Solution owner
C.
Solution owner
Answers
D.
Stakeholder
D.
Stakeholder
Answers
Suggested answer: C
asked 18/09/2024
DAVID STAATZ
40 questions

Question 228

Report
Export
Collapse

Which of the following processes includes tasks and roles, risk categories, schedules for risk management activities, definitions of probability and impact, and the stakeholders' tolerances?

A.
Risk management plan
A.
Risk management plan
Answers
B.
Risk register
B.
Risk register
Answers
C.
Risk analysis
C.
Risk analysis
Answers
D.
Risk response plan
D.
Risk response plan
Answers
Suggested answer: A
asked 18/09/2024
Martynas Abrutis
39 questions

Question 229

Report
Export
Collapse

Which of the following is the process of identifying and assessing factors that may jeopardize the success of a project or the achievement of a goal?

A.
Risk analysis
A.
Risk analysis
Answers
B.
Risk identification
B.
Risk identification
Answers
C.
Risk retention
C.
Risk retention
Answers
D.
Risk communication
D.
Risk communication
Answers
Suggested answer: A
asked 18/09/2024
Dylan Johnson
42 questions

Question 230

Report
Export
Collapse

As a milestone is reached, the project is funded for enough capital to reach the next milestone. This approach is called _________.

A.
Step funding
A.
Step funding
Answers
B.
Phase funding
B.
Phase funding
Answers
C.
Stakeholders funding
C.
Stakeholders funding
Answers
D.
Milestone funding
D.
Milestone funding
Answers
Suggested answer: A