ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers, Page 16

Question list
Search
Search

List of questions

Search

Related questions











A risk manager has identified multiple risks in an innovation project and needs to prioritize the use of resources to respond to the risks. Which analysis will help the risk manager in this situation?

A.

Sensitivity analysis

A.

Sensitivity analysis

Answers
B.

Qualitative analysis

B.

Qualitative analysis

Answers
C.

Statistical analysis

C.

Statistical analysis

Answers
D.

Impact analysis

D.

Impact analysis

Answers
Suggested answer: B

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

A.

Compatibility

A.

Compatibility

Answers
B.

Urgency

B.

Urgency

Answers
C.

Usability

C.

Usability

Answers
D.

Proximity

D.

Proximity

Answers
E.

Detectability

E.

Detectability

Answers
Suggested answer: B, D, E

An organization is embarking on a multi-million-dollar project with numerous identified risks. What should the project risk team do to navigate the risks on this project?

A.

Go for a low-risk threshold of 5% around a cost objective.

A.

Go for a low-risk threshold of 5% around a cost objective.

Answers
B.

Confirm stakeholders risk thresholds based on risk appetites.

B.

Confirm stakeholders risk thresholds based on risk appetites.

Answers
C.

Conduct risk identification to populate the risk register.

C.

Conduct risk identification to populate the risk register.

Answers
D.

Go for a high-risk threshold of 10% around a cost objective.

D.

Go for a high-risk threshold of 10% around a cost objective.

Answers
Suggested answer: C

A risk manager has a well-structured risk management process in place for a complex project with a tight schedule. Despite implementing preventive actions, one of the risks identified in the early stages of the project has still occurred and is now an issue.

What should the risk manager do next?

A.

Meet with the project team to brainstorm potential solutions to the problem.

A.

Meet with the project team to brainstorm potential solutions to the problem.

Answers
B.

Implement the risk response plan to remedy the problem as soon as possible.

B.

Implement the risk response plan to remedy the problem as soon as possible.

Answers
C.

Initiate discussions with the project manager to decide how to manage the problem.

C.

Initiate discussions with the project manager to decide how to manage the problem.

Answers
D.

Escalate the problem to the project sponsor to agree on the best course of action.

D.

Escalate the problem to the project sponsor to agree on the best course of action.

Answers
Suggested answer: B

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

A.

Perform a sensitivity analysis.

A.

Perform a sensitivity analysis.

Answers
B.

Perform a qualitative risk analysis.

B.

Perform a qualitative risk analysis.

Answers
C.

Perform a constraint analysis.

C.

Perform a constraint analysis.

Answers
D.

Perform a root-cause analysis.

D.

Perform a root-cause analysis.

Answers
Suggested answer: B

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

A.

Risk Action Owner

A.

Risk Action Owner

Answers
B.

Risk Owner

B.

Risk Owner

Answers
C.

Project Manager

C.

Project Manager

Answers
D.

Product Manager

D.

Product Manager

Answers
Suggested answer: B

A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.

What should the risk manager do?

A.

Execute the risk response plan defined for the risk.

A.

Execute the risk response plan defined for the risk.

Answers
B.

Postpone the software launch to sort out the technical issue.

B.

Postpone the software launch to sort out the technical issue.

Answers
C.

Meet with the project manager to revisit the project schedule.

C.

Meet with the project manager to revisit the project schedule.

Answers
D.

Assess the impacts and define the response actions with the subject matter experts (SMEs).

D.

Assess the impacts and define the response actions with the subject matter experts (SMEs).

Answers
Suggested answer: A

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

A.

Prioritize after quantitative analysis.

A.

Prioritize after quantitative analysis.

Answers
B.

Perform qualitative analysis.

B.

Perform qualitative analysis.

Answers
C.

Prioritize the stakeholders affected.

C.

Prioritize the stakeholders affected.

Answers
D.

Conduct a subject matter expert (SME) meeting.

D.

Conduct a subject matter expert (SME) meeting.

Answers
Suggested answer: B

During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.

How should the risk manager address this concern?

A.

Compare the actual data with the subject matter expert (SME) criteria.

A.

Compare the actual data with the subject matter expert (SME) criteria.

Answers
B.

Compare the actual data with the historical data.

B.

Compare the actual data with the historical data.

Answers
C.

Compare the actual data with the risk baseline.

C.

Compare the actual data with the risk baseline.

Answers
D.

Compare the actual data with the project sponsor's expectation.

D.

Compare the actual data with the project sponsor's expectation.

Answers
Suggested answer: C

The risk manager loaded the risk register, built the risks into the simulation software, and ran the Monte Carlo analysis The P80 and P90 end dates are the same as the deterministic date.

What should be the risk manager's next step?

A.

Check the schedule for constraints

A.

Check the schedule for constraints

Answers
B.

Decrease the risk consequences

B.

Decrease the risk consequences

Answers
C.

Decrease the number of iterations

C.

Decrease the number of iterations

Answers
D.

Use the P90 date on the risk report

D.

Use the P90 date on the risk report

Answers
Suggested answer: A
Total 201 questions
Go to page: of 21