ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers, Page 15

Question list
Search
Search

List of questions

Search

Related questions











A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the client's vendor, which apparently has been causing all of the issues.

What should the risk manager do first?

A.

Enhance risk identification.

A.

Enhance risk identification.

Answers
B.

Review the contingency reserves.

B.

Review the contingency reserves.

Answers
C.

Create a risk response plan.

C.

Create a risk response plan.

Answers
D.

Review the risk registry.

D.

Review the risk registry.

Answers
Suggested answer: D

Explanation:

The risk registry is a document that records the identified risks, their characteristics, their status, and their responses. It is a key input for risk management and a source of information for project stakeholders. The risk manager should review the risk registry first to understand the current state of the project risks, especially the ones related to the client's vendor, and to evaluate the effectiveness of the risk responses implemented so far. Enhancing risk identification, reviewing the contingency reserves, and creating a risk response plan are possible actions that the risk manager may take after reviewing the risk registry, but they are not the first thing to do.

Reference: PMI Risk Management Professional (PMI-RMP) Exam Content Outline1, PMI Practice Standard for Project Risk Management2, Risk Management Professional (PMI-RMP) Cert Guide3

During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.

Which action should the risk manager take to address this risk?

A.

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.

A.

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.

Answers
B.

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder's team.

B.

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder's team.

Answers
C.

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.

C.

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.

Answers
D.

Add the identified risk to the risk register for future probability and impact analysis.

D.

Add the identified risk to the risk register for future probability and impact analysis.

Answers
Suggested answer: D

Explanation:

Adding the identified risk to the risk register is the best action that the risk manager can take to address this risk. The risk register is a document that records the identified risks, their characteristics, their status, and their responses. By adding the risk to the risk register, the risk manager can ensure that the risk is not overlooked or ignored, and that it will be subjected to further probability and impact analysis to determine its priority and response strategy. Accepting the identified risk because other stakeholders feel that there are higher priority risks to address is not a good practice, as it may lead to overlooking a potentially significant risk that could affect the stakeholder's team. Mitigating the identified risk in order to reduce the probability of impacting the stakeholder's team is not advisable, as it may be a premature or unnecessary action without proper analysis of the risk probability and impact.Escalating the identified risk to the project sponsor and allowing them to determine the best course of action is not appropriate, as it may be an overreaction or a sign of lack of competence from the risk manager, who should be able to handle the risk identification and analysis process.Reference: PMI Risk Management Professional (PMI-RMP) Exam Content Outline1, PMI Practice Standard for Project Risk Management2, Risk Management Professional (PMI-RMP) Cert Guide3

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

A.

The risk categorization

A.

The risk categorization

Answers
B.

The risk simulation

B.

The risk simulation

Answers
C.

The full risk description

C.

The full risk description

Answers
D.

The risk response plan

D.

The risk response plan

Answers
Suggested answer: C

Explanation:

The full risk description is the first thing that the risk manager should complete before moving forward with the risk response planning. The full risk description is a detailed statement that describes the risk, its causes, its effects, and its context. It provides the basis for the risk analysis and the risk response planning.The risk categorization, the risk simulation, and the risk response plan are possible steps that the risk manager may take after completing the full risk description, but they are not the first thing to do.Reference: PMI Risk Management Professional (PMI-RMP) Exam Content Outline1, PMI Practice Standard for Project Risk Management2, Risk Management Professional (PMI-RMP) Cert Guide3

While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.

What should the risk manager do to manage this risk?

A.

Perform time recovery actions.

A.

Perform time recovery actions.

Answers
B.

Execute the prevention plans.

B.

Execute the prevention plans.

Answers
C.

Execute the contingency plans.

C.

Execute the contingency plans.

Answers
D.

Perform change management.

D.

Perform change management.

Answers
Suggested answer: C

Explanation:

Contingency plans are predefined actions that the project team will take if an identified risk event occurs. They are designed to reduce the impact or probability of the risk, or to restore the project to its original objectives. Contingency plans are part of the risk response planning process, and they should be documented in the risk register. In this case, the risk manager should execute the contingency plans to deal with the delays caused by the weather, as they cannot be avoided or mitigated. Performing time recovery actions, executing prevention plans, or performing change management are not appropriate responses for this risk, as they are either reactive, proactive, or corrective measures that do not address the risk directly.Reference: = PMBOK Guide, 6th edition, page 443; The Standard for Risk Management in Portfolios, Programs, and Projects, page 75.

The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.

How should the risk manager document the impact of the residual risk?

A.

Utilize change management tools to request a budget increase from the project sponsor and update the risk register.

A.

Utilize change management tools to request a budget increase from the project sponsor and update the risk register.

Answers
B.

Change the risk identification and description on the risk register to reflect the fact that the residual risk has materialized.

B.

Change the risk identification and description on the risk register to reflect the fact that the residual risk has materialized.

Answers
C.

Close the risk's status on the risk register since the residual risk has now materialized.

C.

Close the risk's status on the risk register since the residual risk has now materialized.

Answers
D.

Review the impact of the residual risk against the budget reserves and document the update in the risk register.

D.

Review the impact of the residual risk against the budget reserves and document the update in the risk register.

Answers
Suggested answer: D

A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite.

What should the risk manager advise the project team to do?

A.

Align the project risk thresholds with the risk appetite of a critical region.

A.

Align the project risk thresholds with the risk appetite of a critical region.

Answers
B.

Align the project risk thresholds with the organizational risk appetite.

B.

Align the project risk thresholds with the organizational risk appetite.

Answers
C.

Concentrate on the risk appetites of the influential stakeholders.

C.

Concentrate on the risk appetites of the influential stakeholders.

Answers
D.

Concentrate on the risk appetites of the vulnerable stakeholders.

D.

Concentrate on the risk appetites of the vulnerable stakeholders.

Answers
Suggested answer: B

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

A.

Remind the project team to keep an open mind

A.

Remind the project team to keep an open mind

Answers
B.

Review the results with the project manager afterward

B.

Review the results with the project manager afterward

Answers
C.

Review published operational experience reports

C.

Review published operational experience reports

Answers
D.

Use the mean answers provided by the project team

D.

Use the mean answers provided by the project team

Answers
Suggested answer: C

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.

What should the risk manager do?

A.

Document the concern over the potential excessive additional cost.

A.

Document the concern over the potential excessive additional cost.

Answers
B.

Manage the potential excessive additional cost as a new risk.

B.

Manage the potential excessive additional cost as a new risk.

Answers
C.

Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.

C.

Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.

Answers
D.

Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project.

D.

Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project.

Answers
Suggested answer: B

A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.

What should the risk manager do first?

A.

Remove the activity padding.

A.

Remove the activity padding.

Answers
B.

Review the risk response plan.

B.

Review the risk response plan.

Answers
C.

Update the risk contingency plan.

C.

Update the risk contingency plan.

Answers
D.

Update the schedule constraints.

D.

Update the schedule constraints.

Answers
Suggested answer: C

A project manager for a large product development project assigned a risk manager to perform the risk management. The project sponsor questions why this project requires a risk manager as it is similar to a previous project with a developed risk strategy.

How should the risk manager explain the need for a risk strategy specific to this project?

A.

A risk strategy is a best practice and ensures quality in the project planning.

A.

A risk strategy is a best practice and ensures quality in the project planning.

Answers
B.

A project specific risk strategy includes enough information to respond to audits and compliance requirements.

B.

A project specific risk strategy includes enough information to respond to audits and compliance requirements.

Answers
C.

A risk strategy ensures alignment of the organizational structure to the specific project.

C.

A risk strategy ensures alignment of the organizational structure to the specific project.

Answers
D.

A risk strategy aligns individual project risk thresholds with organizational risk appetite.

D.

A risk strategy aligns individual project risk thresholds with organizational risk appetite.

Answers
Suggested answer: D
Total 201 questions
Go to page: of 21