PMI PMI-RMP Practice Test - Questions Answers, Page 14
List of questions
Related questions
A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.
Which technique should the risk manager use in this situation?
Brainstorming
Delphi method
Focus group
Checklist analysis
As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?
Close and communicate the results of the risk response actions.
Run a workshop to analyze the effectiveness of the risk plan.
Conduct a risk reserve analysis and document the results.
Verify that all risk response actions have been documented.
A risk manager and project team are managing a software system project, which is expected to be completed within 12 months. The project is currently halfway through, and the team has just delivered the second version of the prototype. During the weekly status meeting, a team member reported that an important stakeholder is facing an issue, which will likely result in a change request that is outside the scope of the current prototype.
What should the risk manager advise the team to do first?
Mitigate the risk by asking the team member to gather more information.
Add the risk to the issue log and revisit it when there is more information.
Arrange a meeting with the stakeholder to discuss the risk and information.
Add the risk to the risk register and gather information about its probability and impact.
In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.
In implementing this plan, which response should the risk manager use?
Exploit
Accept
Share
Enhance
During project development, a risk manager notices that a major update in the country's regulations might be happening in the upcoming months. These changes will affect the materials used in building some of the components of the final product. The project team is unsure if this risk will affect the project negatively or positively.
Which tool should the project team use to determine this?
Sensitivity analysis
Threshold analysis
Reserve analysis
Strengths, weaknesses, opportunities, and threats (SWOT) analysis
Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.
What should the risk manager do to avoid the previous issues?
Use the information for a risk workshop.
Improve monitoring and controlling of activities.
Document the issues in the lessons learned.
Create an issue log to share with the team.
A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?
Evaluate any new risks that are introduced due to the change in scope.
Update the risk management plan to reflect the scope change.
Reassess the identified risks that impact the project scope.
Update the risk register to identify, analyze, and plan a response for any new risk.
In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about to drop their intention to continue executing the project. The risk manager does not understand their decision.
What should the risk manager do next to understand the major stakeholder's decision regarding the project?
Perform a risk impact analysis.
Perform a risk reserve analysis.
Perform a procurement analysis.
Perform a stakeholder impact and influence analysis.
A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.
Which technique should the risk manager use?
Political, economic, social, technological, legal, and environmental (PESTLE) analysis
Strengths, weaknesses, opportunities, and threats (SWOT) analysis
Decision tree analysis
Cost-benefit analysis
In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.
What should the risk manager do?
Update the risk register accordingly and review it in regular project meetings.
Accept the risk because residual risks are often low.
Ask a subject matter expert (SME) to assess the residual risk and take action.
Assign a risk owner and set it as high priority and high impact.
Question