ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers, Page 13

Question list
Search
Search

List of questions

Search

Related questions











A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.

Which kind of numerical analysis should be performed to understand the worst-case scenarios?

A.

Earned value analysis

A.

Earned value analysis

Answers
B.

Qualitative risk analysis

B.

Qualitative risk analysis

Answers
C.

Sensitivity analysis

C.

Sensitivity analysis

Answers
D.

Root cause analysis

D.

Root cause analysis

Answers
Suggested answer: C

Explanation:

sensitivity analysis is a technique that helps to determine which risks have the most potential impact on the project. It examines the extent to which the uncertainty of each project element affects the objective being examined when all other uncertain elements are held at their baseline values. Sensitivity analysis is often used to assess the risk exposure of the project schedule and cost, and to identify the critical risks that need to be managed. In this case, the risk manager needs to understand how the new risk resulting from the delay will affect the project deadline, which is the objective being examined. By performing sensitivity analysis, the risk manager can compare the relative importance and interaction of the new risk with other existing risks, and determine the worst-case scenarios for the project completion date. Sensitivity analysis can also help to prioritize risks for response planning and to develop contingency reserves.This is part of the Perform Quantitative Risk Analysis process in the PMBOK Guide2.Reference:1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline2: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

A.

Strengths, weakness, opportunities, and threats (SWOT) analysis

A.

Strengths, weakness, opportunities, and threats (SWOT) analysis

Answers
B.

Delphi technique

B.

Delphi technique

Answers
C.

Decision tree analysis

C.

Decision tree analysis

Answers
D.

Probability impact matrix

D.

Probability impact matrix

Answers
Suggested answer: B

Explanation:

According to the PMI-RMP Exam Content Outline1, one of the tools and techniques for risk identification is the Delphi technique. This is a method of obtaining expert opinions anonymously and iteratively until a consensus is reached. The Delphi technique can help overcome the problem of SMEs being reluctant to participate in risk identification because it allows them to express their views without fear of criticism or confrontation from other participants. The Delphi technique can also reduce the influence of dominant or biased individuals and encourage honest and independent feedback.Therefore, the best answer is B.Reference:1: PMI-RMP Exam Content Outline, page 8.

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

A.

A potential need to share the space with other machinery

A.

A potential need to share the space with other machinery

Answers
B.

A different type of equipment received before installation

B.

A different type of equipment received before installation

Answers
C.

A time delay during air conditioning installation activities

C.

A time delay during air conditioning installation activities

Answers
D.

A quality nonconformance issue raised during the inspection

D.

A quality nonconformance issue raised during the inspection

Answers
Suggested answer: A

Explanation:

A risk trigger is an indication or warning sign that a risk is about to occur or has occurred. A risk trigger can be an event, a condition, or a situation that signals the onset of a risk. A risk trigger can help the project team to identify and respond to risks in a timely manner. In this case, the lack of space to install air conditioners is a risk with high impact on the project. A potential need to share the space with other machinery is an example of an early risk trigger, because it indicates that the space issue may become a problem in the future. If the project team detects this trigger, they can take proactive actions to avoid or mitigate the risk, such as finding an alternative location, modifying the design, or negotiating with the stakeholders.Reference:PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 102-103.

A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered.

How should the risk manager address these concerns?

A.

Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.

A.

Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.

Answers
B.

Refer to the project charter to find guidelines and stakeholder communication channels.

B.

Refer to the project charter to find guidelines and stakeholder communication channels.

Answers
C.

Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.

C.

Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.

Answers
D.

Rewrite the risk register to include the additional possible risks and inform the stakeholders.

D.

Rewrite the risk register to include the additional possible risks and inform the stakeholders.

Answers
Suggested answer: C

Explanation:

According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline1, one of the tasks in the domain ofRisk Identificationis to review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input on risks throughout the project life cycle1.The stakeholder register is a project document that identifies the project stakeholders, their roles, interests, expectations, influence, and communication requirements2.The stakeholder engagement plan is a component of the project management plan that describes the strategies and actions to promote productive involvement of stakeholders in project decision making and execution3. In this scenario, the risk manager should review these documents to address the concerns of some stakeholders who are complaining that their opinions were not considered in the risk identification process. The risk manager should communicate with the stakeholders according to their preferences and needs, and solicit their input on the project risks using various tools and techniques, such as interviews, surveys, brainstorming, etc. The risk manager should also update the stakeholder register and stakeholder engagement plan as needed to reflect any changes in the stakeholder community or their expectations.The risk manager should not refer to the requirements documentation to confirm stakeholder requirements as they relate to risks, because that is not a direct way to address the stakeholders' concerns, and it may not capture all the potential risks that the stakeholders may identify4.The risk manager should not refer to the project charter to find guidelines and stakeholder communication channels, because the project charter is a high-level document that does not provide detailed information on how to communicate and engage with the stakeholders5.The risk manager should not rewrite the risk register to include the additional possible risks and inform the stakeholders, because that is a premature and presumptuous action that may not reflect the actual views and inputs of the stakeholders, and it may create more confusion and dissatisfaction among them6.Reference:1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline, page 82: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 5133: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 5184: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 1525: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 776: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 414.

An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?

A.

Update the risk register

A.

Update the risk register

Answers
B.

Meet with the project's stakeholders

B.

Meet with the project's stakeholders

Answers
C.

Revise the risk management plan

C.

Revise the risk management plan

Answers
D.

Ensure sufficient resources are available

D.

Ensure sufficient resources are available

Answers
Suggested answer: C

Explanation:

According to the PMBOK Guide1, the risk management plan is a component of the project management plan that describes how risk management activities will be structured and performed. It provides guidance on how the project team will identify, analyze, respond, monitor, and control risks throughout the project life cycle. The risk management plan should be reviewed and updated whenever there are changes in the project scope, schedule, budget, or objectives, as these changes may introduce new risks or affect the existing ones. In this case, the organization's decision to accelerate a key project is a significant change that may alter the risk profile of the project. Therefore, the first action for the project risk manager to take is to revise the risk management plan to reflect the new situation and ensure that the risk management processes are aligned with the project objectives and constraints.This is part of the Plan Risk Management process in the PMBOK Guide1.Reference:1: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition

A project team has just initiated a large project to move an organization's headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.

What should the risk manager consider?

A.

Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.

A.

Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.

Answers
B.

The ideal solution is to find alternate documents that provide good visibility on the environment.

B.

The ideal solution is to find alternate documents that provide good visibility on the environment.

Answers
C.

The risk identification process can be carried out as long as the project statement is available.

C.

The risk identification process can be carried out as long as the project statement is available.

Answers
D.

Risk evaluation will be challenging without these elements as a frame of reference.

D.

Risk evaluation will be challenging without these elements as a frame of reference.

Answers
Suggested answer: D

Explanation:

According to the PMI-RMP Exam Content Outline1, one of the tasks in the domain of risk identification is to ''review project documents, assumptions, and constraints, and understand the project environment and organizational factors to identify risks''. The project charter, work breakdown structure (WBS), and scope statement are essential project documents that provide information about the project objectives, deliverables, requirements, assumptions, and constraints. Without these elements, the risk manager will have difficulty identifying and evaluating the risks that may affect the project.Therefore, the best answer is D.Reference:1: PMI-RMP Exam Content Outline, page 7.

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

A.

Review project schedule estimates.

A.

Review project schedule estimates.

Answers
B.

Change the response strategies.

B.

Change the response strategies.

Answers
C.

Reduce the contingency reserves.

C.

Reduce the contingency reserves.

Answers
D.

Conduct a risk planning workshop.

D.

Conduct a risk planning workshop.

Answers
Suggested answer: D

Explanation:

The risk manager should conduct a risk planning workshop with senior management and other key stakeholders to review the risk management plan, the risk register, and the contingency reserves. The risk manager should explain the purpose and benefits of contingency reserves, and how they are calculated and allocated based on the risk exposure of the project. The risk manager should also discuss the potential impact of removing or reducing the contingency reserves on the project objectives, scope, schedule, cost, and quality. The risk manager should facilitate a collaborative decision-making process to reach a consensus on the best course of action for the project.Reference:PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 77-78, 92-93.

A risk manager is assigned to a new system deployment project with a strict contractually agreed-on schedule. One of the key risks identified is the availability of experts because many are shared on other strategic projects in the organization.

What should the risk manager do to address this situation?

A.

Implement a disciplined tracking method and report to stakeholders accordingly.

A.

Implement a disciplined tracking method and report to stakeholders accordingly.

Answers
B.

Call for a project team meeting to review risk strategies and make required adjustments.

B.

Call for a project team meeting to review risk strategies and make required adjustments.

Answers
C.

Escalate the staffing topic to the sponsor and request more budget for contingencies.

C.

Escalate the staffing topic to the sponsor and request more budget for contingencies.

Answers
D.

Revisit the project charter for scope adjustments and sign them off with the customer.

D.

Revisit the project charter for scope adjustments and sign them off with the customer.

Answers
Suggested answer: A

Explanation:

According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline1, one of the tasks in the domain ofRisk Responseis to call for a project team meeting to review risk strategies and make required adjustments, as needed, based on risk monitoring and reporting1. In this scenario, the risk manager should do this to address the situation of the availability of experts, which is a key risk for the project. The project team meeting will help the risk manager and the project team to evaluate the effectiveness of the current risk response plan, identify any new risks or changes in existing risks, and develop alternative risk strategies and actions to deal with the staffing issue. The project team meeting will also facilitate the communication and collaboration among the project team members and other stakeholders, and ensure that the project objectives and expectations are aligned.The risk manager should not implement a disciplined tracking method and report to stakeholders accordingly, because that is not a proactive risk response strategy, but rather a passive risk monitoring and reporting technique2.The risk manager should not escalate the staffing topic to the sponsor and request more budget for contingencies, because that is not a feasible or appropriate risk response strategy, as it does not address the root cause of the risk or provide a solution to the problem3.The risk manager should not revisit the project charter for scope adjustments and sign them off with the customer, because that is not a risk response strategy, but rather a scope management process that may have negative impacts on the project quality, cost, and schedule, and may violate the contractual agreement with the customer4.Reference:1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline, page 102: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4563: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4364: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 133.

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

A.

Assess the identified secondary risk.

A.

Assess the identified secondary risk.

Answers
B.

Implement the risk response plan.

B.

Implement the risk response plan.

Answers
C.

Implement the risk contingency plan.

C.

Implement the risk contingency plan.

Answers
D.

Communicate the identified residual risk.

D.

Communicate the identified residual risk.

Answers
Suggested answer: A

Explanation:

According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline1, a secondary risk is a risk that arises as a direct result of implementing a risk response to a specific risk. In this case, the risk response is to contract an external vendor to provide additional capacity and expertise to the project team. The secondary risk is the confidentiality risk that the contracts department has identified. The risk manager should assess the secondary risk to determine its probability, impact, and priority, and to plan appropriate responses.This is part of the Perform Qualitative Risk Analysis and Plan Risk Responses processes in the PMBOK Guide2.Reference:1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline2: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition

A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

A.

Risk management plan

A.

Risk management plan

Answers
B.

Clients' credit scores

B.

Clients' credit scores

Answers
C.

Organization's mission and vision

C.

Organization's mission and vision

Answers
D.

Historical data from the credit portfolio

D.

Historical data from the credit portfolio

Answers
Suggested answer: A

Explanation:

According to the PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1, the risk manager should request the risk management plan first from the project sponsor to identify major risks. This is because:

The risk management plan is a document that describes how risk management activities will be planned, structured, and performed throughout the project life cycle. The risk management plan provides guidance and direction for the risk manager and the project team on how to identify, analyze, prioritize, respond, and monitor risks, as well as how to allocate resources, define roles and responsibilities, establish risk categories, and document risk-related information.

The risk management plan is a key input for the risk identification process, which is the process of determining which risks may affect the project and documenting their characteristics. The risk identification process involves using various tools and techniques, such as brainstorming, interviews, checklists, assumptions and constraints analysis, SWOT analysis, expert judgment, and data gathering, to generate a comprehensive list of potential risks that may impact the project objectives, such as scope, schedule, cost, quality, or stakeholder satisfaction.

The risk management plan helps the risk manager to identify major risks by providing the following information:

The risk management strategy, which defines the approach and methodology for managing risks, including the level of detail, rigor, and frequency of the risk management activities, and the alignment with the project management plan and the organization's policies and procedures.

The risk thresholds, which specify the acceptable level of risk exposure for the project and its objectives, based on the risk appetite, tolerance, and attitude of the project sponsor and other key stakeholders.

The risk categories, which are a group of potential causes of risk that can be used to structure and organize the identified risks into a hierarchical structure, such as a risk breakdown structure (RBS). The risk categories can be derived from various sources, such as the project scope statement, the work breakdown structure (WBS), the organizational process assets, or the industry standards and practices.

The roles and responsibilities, which define the authority and accountability of the project team members and other stakeholders involved in the risk management process, such as the risk manager, the risk owner, the risk committee, the risk auditor, and the risk reviewer.

The resources, which specify the budget, time, and human resources allocated for the risk management process, as well as the tools, techniques, and software applications that will be used to support the risk management activities.

The communication and reporting, which describe the type, format, content, frequency, and distribution of the risk-related information and reports that will be shared among the project team and other stakeholders, such as the risk register, the risk report, the risk dashboard, and the risk audit report.

The other options are not the best documents to request first from the project sponsor to identify major risks because:

The clients' credit scores are a specific type of data that can be used to assess the credit risk of the loans, but they do not provide a comprehensive view of all the potential risks that may affect the project, such as technical, operational, legal, regulatory, or market risks.

The organization's mission and vision are high-level statements that describe the purpose, values, and goals of the organization, but they do not provide specific guidance or direction on how to manage risks for the project, such as the risk management strategy, methodology, or tools.

The historical data from the credit portfolio are a source of information that can be used to analyze the past performance and trends of the loans, but they do not reflect the current or future uncertainties and opportunities that may impact the project, such as changes in customer behavior, technology, competition, or regulation.

PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1

Risk Management Professional (PMI-RMP) Exam Cert Guide2

Total 201 questions
Go to page: of 21