PMI PMI-RMP Practice Test - Questions Answers, Page 13
List of questions
Related questions
A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.
Which kind of numerical analysis should be performed to understand the worst-case scenarios?
Earned value analysis
Qualitative risk analysis
Sensitivity analysis
Root cause analysis
During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?
Strengths, weakness, opportunities, and threats (SWOT) analysis
Delphi technique
Decision tree analysis
Probability impact matrix
During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?
A potential need to share the space with other machinery
A different type of equipment received before installation
A time delay during air conditioning installation activities
A quality nonconformance issue raised during the inspection
A risk manager for a cross-functional project is initiating the risk identification process. The risk manager conducted some meetings for stakeholders to express their concerns, but some stakeholders are complaining that their opinions were not considered.
How should the risk manager address these concerns?
Refer to the requirements documentation to confirm stakeholder requirements as they relate to risks.
Refer to the project charter to find guidelines and stakeholder communication channels.
Review the stakeholder register and stakeholder engagement plan to communicate and solicit stakeholder input.
Rewrite the risk register to include the additional possible risks and inform the stakeholders.
An organization faces immense competition in the market and decides to accelerate a key project. What is the first action for the project risk manager to take?
Update the risk register
Meet with the project's stakeholders
Revise the risk management plan
Ensure sufficient resources are available
A project team has just initiated a large project to move an organization's headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.
What should the risk manager consider?
Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.
The ideal solution is to find alternate documents that provide good visibility on the environment.
The risk identification process can be carried out as long as the project statement is available.
Risk evaluation will be challenging without these elements as a frame of reference.
A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.
What should the risk manager do in this scenario?
Review project schedule estimates.
Change the response strategies.
Reduce the contingency reserves.
Conduct a risk planning workshop.
A risk manager is assigned to a new system deployment project with a strict contractually agreed-on schedule. One of the key risks identified is the availability of experts because many are shared on other strategic projects in the organization.
What should the risk manager do to address this situation?
Implement a disciplined tracking method and report to stakeholders accordingly.
Call for a project team meeting to review risk strategies and make required adjustments.
Escalate the staffing topic to the sponsor and request more budget for contingencies.
Revisit the project charter for scope adjustments and sign them off with the customer.
An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.
What should the risk manager do next?
Assess the identified secondary risk.
Implement the risk response plan.
Implement the risk contingency plan.
Communicate the identified residual risk.
A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?
Risk management plan
Clients' credit scores
Organization's mission and vision
Historical data from the credit portfolio
Question