ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers, Page 12

Question list
Search
Search

List of questions

Search

Related questions











A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.

What will be the main output of this meeting?

A.

Evaluating the project's probability of success

A.

Evaluating the project's probability of success

Answers
B.

Identifying threats and opportunities

B.

Identifying threats and opportunities

Answers
C.

Evaluating the project's impact

C.

Evaluating the project's impact

Answers
D.

Performing a qualitative analysis

D.

Performing a qualitative analysis

Answers
Suggested answer: B

Explanation:

The main output of the stakeholder meeting in the initiation phase is to identify threats and opportunities that may impact the project in a positive or negative way. This information will be used to develop the risk management plan.

The meeting that the project stakeholders are invited to in the initiation phase is part of the Identify Risks process. The purpose of this process is to identify the risks that may affect the project objectives in a positive or negative way, and to document their characteristics. The main output of this process is the risk register, which is a document that contains the list of identified risks, their causes, potential responses, and other relevant information. The risk register is an essential input for the subsequent risk management processes, such as Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis, Plan Risk Responses, and Monitor Risks. Therefore, the correct answer is B. Identifying threats and opportunities.Reference:PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 79-80, 86-87.

When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

A.

Select the strategies with the least overall impact to resources.

A.

Select the strategies with the least overall impact to resources.

Answers
B.

Select the strategies with the least financial impact.

B.

Select the strategies with the least financial impact.

Answers
C.

Select the strategies with the greatest overall positive influence.

C.

Select the strategies with the greatest overall positive influence.

Answers
D.

Select the strategies with the greatest benefit to stakeholders.

D.

Select the strategies with the greatest benefit to stakeholders.

Answers
Suggested answer: C

Explanation:

The overall goal of selecting strategies during the Plan Risk Response activity is to choose those strategies that have the greatest overall positive influence on the project, considering factors such as cost, schedule, and resources.

According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline1, one of the tasks in the domain ofRisk Responseis to select risk response strategies based on the risk appetite and tolerance of the organization and stakeholders1. The overall goal of selecting risk response strategies is to select the strategies with the greatest overall positive influence on the project objectives, such as scope, schedule, cost, quality, etc.The risk response strategies should aim to enhance the opportunities and reduce the threats to the project, while considering the cost-benefit analysis, the feasibility, and the alignment with the project goals and stakeholder expectations2.The risk response strategies should not be selected based on the least overall impact to resources, because that may not be the most effective or efficient way to address the risks, and it may ignore the potential benefits of some strategies that may require more resources but also deliver more value3. The risk response strategies should not be selected based on the least financial impact, because that may not be the most relevant or comprehensive criterion to evaluate the risks, and it may overlook other aspects of the project, such as quality, customer satisfaction, reputation, etc.that may also be affected by the risks4.The risk response strategies should not be selected based on the greatest benefit to stakeholders, because that may not be the most realistic or achievable goal, and it may create conflicts or trade-offs among different stakeholder groups that may have different or competing interests, needs, and expectations5.Reference:1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline, page 102: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4403: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4414: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4425: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 518.

An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.

What should the risk management expert recommend the agency do first to identify risks and develop the handbook?

A.

Follow standard risk Identification tools dedicated for agriculture and tailor them to the environment.

A.

Follow standard risk Identification tools dedicated for agriculture and tailor them to the environment.

Answers
B.

Hire an agriculture expert who can develop the required handbook and discuss it with the agriculture minister.

B.

Hire an agriculture expert who can develop the required handbook and discuss it with the agriculture minister.

Answers
C.

Prepare a list of the key resources that will be used to compile a risk management plan.

C.

Prepare a list of the key resources that will be used to compile a risk management plan.

Answers
D.

Conduct meetings, facilitated workshops, and interviews with stakeholders to identify potential risks.

D.

Conduct meetings, facilitated workshops, and interviews with stakeholders to identify potential risks.

Answers
Suggested answer: D

Explanation:

According to the PMBOK Guide1, risk identification is the process of determining which risks may affect the project and documenting their characteristics. It involves the use of various techniques to gather information from different sources and perspectives, such as stakeholders, experts, historical data, assumptions, and environmental factors. Some of the common techniques for risk identification are meetings, facilitated workshops, interviews, brainstorming, checklists, questionnaires, SWOT analysis, and root cause analysis. These techniques help to elicit the knowledge and opinions of the participants, and to generate a comprehensive list of potential risks that can be further analyzed and prioritized. In this case, the risk management expert should recommend the agency to conduct meetings, facilitated workshops, and interviews with stakeholders to identify potential risks and develop the handbook. This will help to understand the context and objectives of the agency, the expectations and concerns of the farmers and landlords, the challenges and opportunities in the agriculture sector, and the possible sources and impacts of uncertainty. The risk management expert can then use the information gathered from these techniques to create a risk register and a risk management plan, which can form the basis of the handbook.This is part of the Identify Risks process in the PMBOK Guide1.Reference:1: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition

Engaging stakeholders through meetings, workshops, and interviews is crucial for risk identification, as it allows the agency to gather diverse perspectives and insights on potential risks. This approach is more effective than relying solely on standard tools or hiring an expert.

When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.

How does centralizing the risk management function help resolve the problem?

A.

Enhance the process of identification of different Individual project risks.

A.

Enhance the process of identification of different Individual project risks.

Answers
B.

Allows monitoring the impact against the overall project risk exposure.

B.

Allows monitoring the impact against the overall project risk exposure.

Answers
C.

Establishes risk sources and ownership for trigger monitoring.

C.

Establishes risk sources and ownership for trigger monitoring.

Answers
D.

Creates a single repository for all project risk documents.

D.

Creates a single repository for all project risk documents.

Answers
Suggested answer: B

Explanation:

Centralizing the risk management function enables the organization to have a consistent approach to reporting risks and their impacts. This allows for better monitoring of the impact against the overall project risk exposure, which helps in making informed decisions and allocating resources effectively.

According to the PMI-RMP Exam Content Outline1, one of the tasks in the domain of risk governance is to ''establish and maintain a centralized risk management function to support the project and organizational objectives''. A centralized risk management function can help resolve the problem of inconsistent risk reporting by providing a common framework, methodology, and standards for risk management across the organization. One of the benefits of centralizing the risk management function is that it allows monitoring the impact of individual project risks against the overall project risk exposure, as well as the organizational risk appetite and tolerance. This can help the CEO and other senior management to make informed decisions and allocate resources accordingly. Therefore, the best answer is B.

Which statement describes the risk portrayed on the risk matrix heat map below?

A.

The risk has a probability of 60% of occurrence and a medium impact rating.

A.

The risk has a probability of 60% of occurrence and a medium impact rating.

Answers
B.

The risk has a probability of 40% of occurrence and a high impact rating.

B.

The risk has a probability of 40% of occurrence and a high impact rating.

Answers
C.

The risk has a high impact and probability of occurring.

C.

The risk has a high impact and probability of occurring.

Answers
D.

The risk has a low probability and high impact rating.

D.

The risk has a low probability and high impact rating.

Answers
Suggested answer: B

Explanation:

The risk matrix heat map is a graphical tool that displays the probability and impact of risks in a project. The horizontal axis represents the probability of occurrence, and the vertical axis represents the impact rating. The colors indicate the level of risk exposure, from green (low) to red (high). The risk in question is located in the upper right quadrant of the matrix, which means it has a high impact rating. The probability of occurrence can be estimated by looking at the scale on the horizontal axis. The risk is slightly to the left of the 50% mark, which means it has a probability of occurrence of about 40%. Therefore, the correct statement that describes the risk is B. The risk has a probability of 40% of occurrence and a high impact rating.Reference:PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 104-105.

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?

A.

Escalate the problem to the project sponsors.

A.

Escalate the problem to the project sponsors.

Answers
B.

Execute the approved risk response plan.

B.

Execute the approved risk response plan.

Answers
C.

Negotiate with the supplier to resolve the problem.

C.

Negotiate with the supplier to resolve the problem.

Answers
D.

Assign a team member to update the issue leg.

D.

Assign a team member to update the issue leg.

Answers
Suggested answer: B

Explanation:

According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline1, one of the tasks in the domain ofRisk Responseis to execute the approved risk response plan in accordance with project guidelines and procedures1.A risk response plan is a component of the project management plan that describes the agreed-upon and funded actions to address the project risks, both positive and negative2. In this scenario, the risk manager should execute the approved risk response plan to deal with the new risk that appears when requesting fuel from another supplier, which will cause delays with several other projects.The risk response plan should have been developed and approved during the risk response planning process, which involves selecting and prioritizing the appropriate risk strategies and actions for each risk3.The risk response plan should also be aligned with the project guidelines and procedures, which are the rules and directions that define the project's scope, schedule, cost, quality, and other aspects4.The risk manager should not escalate the problem to the project sponsors, because that is not a risk response strategy, but rather a way to seek higher-level authority or support for a risk that is outside the project's scope or influence5.The risk manager should not negotiate with the supplier to resolve the problem, because that is not a risk response strategy, but rather a procurement management technique that involves reaching a mutually acceptable agreement with the supplier on the terms and conditions of the contract6.The risk manager should not assign a team member to update the issue log, because that is not a risk response strategy, but rather a risk monitoring and reporting technique that involves tracking and documenting the issues that have occurred or are currently affecting the project7.Reference:1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline, page 102: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4143: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4404: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 385: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4376: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4717: What Is an Issue Log?Templates & Tips7.

A project manager wants to introduce a new technology to improve a project's performance. However, there are some costs associated that are beyond the current budget, and the proposed technology has not been applied to any previous company projects.

What should the project manager do in this situation?

A.

Escalate this initiative to project decision makers and sponsors.

A.

Escalate this initiative to project decision makers and sponsors.

Answers
B.

Accept the fact that there is a risk associated with this new technology.

B.

Accept the fact that there is a risk associated with this new technology.

Answers
C.

Take advantage of this opportunity of Improving the project performance.

C.

Take advantage of this opportunity of Improving the project performance.

Answers
D.

Outsource the implementation of the new technology as soon as possible.

D.

Outsource the implementation of the new technology as soon as possible.

Answers
Suggested answer: C

Explanation:

The project manager should escalate this initiative to project decision makers and sponsors, as they have the authority to approve changes in budget and scope. They can evaluate the potential benefits and associated with the new technology and make an informed decision on whether to proceed.

According to the PMBOK Guide1, an opportunity is a risk that would have a positive effect on one or more project objectives if it occurs. Opportunities are uncertain events or conditions that can enhance or facilitate the achievement of project goals, such as cost savings, schedule acceleration, quality improvement, or scope expansion. A project manager should take advantage of opportunities by implementing risk responses that seek to maximize their probability and/or positive impact. In this case, the project manager wants to introduce a new technology to improve the project's performance, which is an opportunity for the project. The project manager should take advantage of this opportunity by planning and executing appropriate risk responses, such as exploiting, enhancing, sharing, or accepting the opportunity.This is part of the Plan Risk Responses and Implement Risk Responses processes in the PMBOK Guide1.Reference:1: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition.

A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.

Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)

A.

Verify whether or not any identified risks might occur and implement the risk response plan.

A.

Verify whether or not any identified risks might occur and implement the risk response plan.

Answers
B.

Regularly check and report on the status of risks identified according to their prioritization.

B.

Regularly check and report on the status of risks identified according to their prioritization.

Answers
C.

Monitor the status and oversee execution of the risk response plan for each identified risk.

C.

Monitor the status and oversee execution of the risk response plan for each identified risk.

Answers
D.

Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.

D.

Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.

Answers
E.

Allocate and lock in project resources according to the initial risk prioritization for all identified risks.

E.

Allocate and lock in project resources according to the initial risk prioritization for all identified risks.

Answers
Suggested answer: B, C, D

Explanation:

According to the PMI-RMP Exam Content Outline1, one of the domains of the PMI-RMP certification is risk monitoring and reporting. This domain includes tasks such as ''monitor and report on risk metrics and trends'', ''monitor the status of risk response activities and update risk register and risk report accordingly'', and ''monitor and control project contingency and management reserves''. These tasks imply that the risk manager should regularly check and report on the status of risks identified according to their prioritization (B), monitor the status and oversee execution of the risk response plan for each identified risk , and ensure management reserves are sufficient to cover the mitigation plans for all identified risks (D). These actions will help the risk manager to ensure the risk management plan remains effective during the project timeframe. Therefore, the best answers are B, C, and D.

A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.

What should the risk manager do first?

A.

Develop a residual risk management plan to manage the residual risks.

A.

Develop a residual risk management plan to manage the residual risks.

Answers
B.

Analyze, document, and communicate the residual risks to stakeholders.

B.

Analyze, document, and communicate the residual risks to stakeholders.

Answers
C.

Record the residual risks in the watch list for future reference.

C.

Record the residual risks in the watch list for future reference.

Answers
D.

Implement the contingency plan when the residual risks occur.

D.

Implement the contingency plan when the residual risks occur.

Answers
Suggested answer: B

Explanation:

Residual risks are the risks that remain after the risk response plan has been implemented. They are the risks that are accepted by the project team and stakeholders as part of the project. Residual risks may have low probability or impact, but they still need to be monitored and controlled throughout the project. The first thing that the risk manager should do when a risk owner identifies and reports some residual risks is to analyze, document, and communicate them to the relevant stakeholders. The risk manager should assess the probability and impact of the residual risks, and determine if they require any further response or contingency plan. The risk manager should also update the risk register and the risk report with the information about the residual risks, and share them with the stakeholders who need to be aware of them. This will help the project team and stakeholders to be prepared for any potential occurrence of the residual risks, and to take appropriate actions if needed.Reference:PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 94-95, 101.

A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.

Which response should the risk manager recommend for these risk items?

A.

Mitigate

A.

Mitigate

Answers
B.

Accept

B.

Accept

Answers
C.

Enhance

C.

Enhance

Answers
D.

Exploit

D.

Exploit

Answers
Suggested answer: B

Explanation:

According to the PMI Risk Management Professional (PMI-RMP) Examination Content Outline1, one of the tasks in the domain ofRisk Responseis to recommend risk response strategies based on the risk appetite and tolerance of the organization and stakeholders1.One of the strategies for negative risks or threats isrisk acceptance, which involves acknowledging the existence of a threat and making a conscious decision to accept it without taking any action2. In this scenario, the risk manager should recommend risk acceptance for the risk items that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.Risk acceptance is appropriate when the risk exposure is low, the cost of other responses is high, or the risk response is outside the scope or influence of the project3.The risk manager should not recommend risk mitigation, which involves reducing the probability and/or impact of a threat2.The risk manager should not recommend risk enhancement, which is a strategy for positive risks or opportunities, not negative risks or threats2.The risk manager should not recommend risk exploitation, which is also a strategy for positive risks or opportunities, not negative risks or threats2.Reference:1: PMI Risk Management Professional (PMI-RMP) Examination Content Outline, page 102: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 4363: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 437.

Total 201 questions
Go to page: of 21