PMI PMI-RMP Practice Test - Questions Answers, Page 12
List of questions
Related questions
A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.
What will be the main output of this meeting?
Evaluating the project's probability of success
Identifying threats and opportunities
Evaluating the project's impact
Performing a qualitative analysis
When selecting strategies as an activity of Plan Risk Response, what is the overall goal?
Select the strategies with the least overall impact to resources.
Select the strategies with the least financial impact.
Select the strategies with the greatest overall positive influence.
Select the strategies with the greatest benefit to stakeholders.
An agriculture government agency faces different challenges with farmers and landlords In implementing its ambitious growth strategy. The agency decided to establish an enterprise risk management unit to identify risks, analyze risks, and provide a handbook showing how to handle the surrounding uncertainty.
What should the risk management expert recommend the agency do first to identify risks and develop the handbook?
Follow standard risk Identification tools dedicated for agriculture and tailor them to the environment.
Hire an agriculture expert who can develop the required handbook and discuss it with the agriculture minister.
Prepare a list of the key resources that will be used to compile a risk management plan.
Conduct meetings, facilitated workshops, and interviews with stakeholders to identify potential risks.
When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.
How does centralizing the risk management function help resolve the problem?
Enhance the process of identification of different Individual project risks.
Allows monitoring the impact against the overall project risk exposure.
Establishes risk sources and ownership for trigger monitoring.
Creates a single repository for all project risk documents.
Which statement describes the risk portrayed on the risk matrix heat map below?
The risk has a probability of 60% of occurrence and a medium impact rating.
The risk has a probability of 40% of occurrence and a high impact rating.
The risk has a high impact and probability of occurring.
The risk has a low probability and high impact rating.
A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.
After performing a detailed analysis, what should the risk manager do?
Escalate the problem to the project sponsors.
Execute the approved risk response plan.
Negotiate with the supplier to resolve the problem.
Assign a team member to update the issue leg.
A project manager wants to introduce a new technology to improve a project's performance. However, there are some costs associated that are beyond the current budget, and the proposed technology has not been applied to any previous company projects.
What should the project manager do in this situation?
Escalate this initiative to project decision makers and sponsors.
Accept the fact that there is a risk associated with this new technology.
Take advantage of this opportunity of Improving the project performance.
Outsource the implementation of the new technology as soon as possible.
A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.
Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)
Verify whether or not any identified risks might occur and implement the risk response plan.
Regularly check and report on the status of risks identified according to their prioritization.
Monitor the status and oversee execution of the risk response plan for each identified risk.
Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.
Allocate and lock in project resources according to the initial risk prioritization for all identified risks.
A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.
What should the risk manager do first?
Develop a residual risk management plan to manage the residual risks.
Analyze, document, and communicate the residual risks to stakeholders.
Record the residual risks in the watch list for future reference.
Implement the contingency plan when the residual risks occur.
A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.
Which response should the risk manager recommend for these risk items?
Mitigate
Accept
Enhance
Exploit
Question