PMI PMI-RMP Practice Test - Questions Answers, Page 10
List of questions
Related questions
While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?
Issue log
Change log
Assumption log
Risk-adjusted back log
When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)
Request a contingency reserve from management
Arrange a team meeting, review the project's scope, and discuss dependency mapping
Ensure participants review relevant documents before attending the meeting
Ensure that all the relevant stakeholders participate
Update the risk register during the team meeting.
After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.
How could the risk manager have avoided the board's response?
Engaging the key stakeholders during the prioritization process
Prioritizing the risks based on the project sponsor's risk appetite
Engaging with the project sponsor before presenting to the board
Working with an established industry standard prioritization method
A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team's tasks have yet to be completed.
What should the risk manager do next?
Start a quantitative analysis to understand the impact.
Crash the schedule to mitigate the risk consequences.
Transfer the risk to the external team.
Ask the risk owners to review the risk response plan.
A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?
Execute the security risks contingency plan.
Get a report of customers affected by the risk.
Identify residual and secondary risks.
Coordinate a response with the risk owner.
During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.
What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?
Reinforce to the stakeholders that the risk identification was done properly during the last sprint.
Highlight the importance of agreeing on the risk identification to avoid further delays.
Conduct a separate meeting to show the risk identification analysis to the stakeholders.
Ensure that the most knowledgeable members of the team validate risk identification processes.
Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?
When the forecast activity date has been met or exceeded
When the stakeholders agree a risk is no longer applicable
When the risk has been realized and can no longer happen again
When iterative data analysis determines the risk is not applicable
The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.
What is this an example of?
Risk responses
Risk triggers
Risk registers
Risk categories
Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.
What will help calculate the impact?
Risk analysis
Risk identification
Risk treatment
Risk evaluation
A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.
What should the risk manager do next to visually organize the risks?
Develop an affinity diagram
Perform the analytical hierarchy process
Perform a SWOT analysis
Assign probability and impact
Question