ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers, Page 10

Question list
Search
Search

List of questions

Search

Related questions











While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

A.

Issue log

A.

Issue log

Answers
B.

Change log

B.

Change log

Answers
C.

Assumption log

C.

Assumption log

Answers
D.

Risk-adjusted back log

D.

Risk-adjusted back log

Answers
Suggested answer: D

Explanation:

The stakeholders should prepare a risk-adjusted backlog when making decisions on how to respond to known and new risks. A risk-adjusted backlog helps prioritize work items based on their risk level and potential impact on the project.

A risk-adjusted backlog is an artifact that reflects the prioritization of the product backlog items based on their risk exposure. It is used to plan for the execution phase of an agile project, where the stakeholders can decide how to respond to known and new risks by selecting the most valuable and least risky items to deliver. A risk-adjusted backlog can help the stakeholders to optimize the value delivery and reduce the uncertainty of the project outcomes.Reference:PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 113; PMI, Agile Practice Guide, 2017, p. 54.

When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

A.

Request a contingency reserve from management

A.

Request a contingency reserve from management

Answers
B.

Arrange a team meeting, review the project's scope, and discuss dependency mapping

B.

Arrange a team meeting, review the project's scope, and discuss dependency mapping

Answers
C.

Ensure participants review relevant documents before attending the meeting

C.

Ensure participants review relevant documents before attending the meeting

Answers
D.

Ensure that all the relevant stakeholders participate

D.

Ensure that all the relevant stakeholders participate

Answers
E.

Update the risk register during the team meeting.

E.

Update the risk register during the team meeting.

Answers
Suggested answer: B, D

Explanation:

According to the PMBOK Guide, one of the tools and techniques for the identify risks process isdata gathering. Data gathering is the process of collecting information from various sources to identify potential risks that may affect the project objectives.Some of the data gathering techniques are brainstorming, interviews, checklists, assumption and constraint analysis, and document analysis1. To conduct a risk identification exercise using data gathering techniques, the risk manager should take the following actions:

Arrange a team meeting, review the project's scope, and discuss dependency mapping. This action can help the risk manager to facilitate a brainstorming session with the project team and other subject matter experts, where they can generate a list of potential risks based on the project scope and the dependencies among the project activities.Dependency mapping is a technique that helps to identify the relationships and interdependencies among the project components, such as tasks, resources, deliverables, and stakeholders2. By reviewing the project scope and discussing the dependency mapping, the risk manager can ensure that the risk identification exercise covers all the relevant aspects of the project and does not miss any important risk sources.

Ensure that all the relevant stakeholders participate. This action can help the risk manager to obtain different perspectives and insights from the stakeholders who have different roles, interests, and expectations in the project. Stakeholders are individuals or groups who can affect or be affected by the project outcomes. They may have valuable information, experience, or expertise that can help to identify potential risks that may not be obvious to the project team.By ensuring that all the relevant stakeholders participate in the risk identification exercise, the risk manager can increase the comprehensiveness and accuracy of the risk identification process and foster stakeholder engagement and buy-in1.Reference: PMBOK Guide, 6th edition, pages 397-399, 414-4151; Mastering the PMI Risk Management Professional (PMI-RMP) Exam, page 70

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board's response?

A.

Engaging the key stakeholders during the prioritization process

A.

Engaging the key stakeholders during the prioritization process

Answers
B.

Prioritizing the risks based on the project sponsor's risk appetite

B.

Prioritizing the risks based on the project sponsor's risk appetite

Answers
C.

Engaging with the project sponsor before presenting to the board

C.

Engaging with the project sponsor before presenting to the board

Answers
D.

Working with an established industry standard prioritization method

D.

Working with an established industry standard prioritization method

Answers
Suggested answer: A

Explanation:

According to the PMBOK Guide, risk prioritization is the process of assigning a level of importance to each identified risk based on its probability and impact, as well as other factors such as urgency, stakeholder tolerance, and project objectives. Risk prioritization helps the project team to focus on the most significant risks and allocate resources accordingly. One of the tools and techniques for risk prioritization is stakeholder engagement, which involves involving the key stakeholders in the risk analysis and decision making process. Stakeholder engagement helps to ensure that the risk prioritization reflects the expectations and preferences of the stakeholders, and that they are aware of and agree with the results. By engaging the key stakeholders during the prioritization process, the risk manager could have avoided the board's request to sort the risks differently, as the board would have been part of the process and would have accepted the outcome.Reference: = PMBOK Guide, 6th edition, pages 406-407; The Standard for Risk Management in Portfolios, Programs, and Projects, page 67.

A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team's tasks have yet to be completed.

What should the risk manager do next?

A.

Start a quantitative analysis to understand the impact.

A.

Start a quantitative analysis to understand the impact.

Answers
B.

Crash the schedule to mitigate the risk consequences.

B.

Crash the schedule to mitigate the risk consequences.

Answers
C.

Transfer the risk to the external team.

C.

Transfer the risk to the external team.

Answers
D.

Ask the risk owners to review the risk response plan.

D.

Ask the risk owners to review the risk response plan.

Answers
Suggested answer: D

Explanation:

According to the PMBOK Guide, the risk response plan is the set of actions that the project team will take to address the identified risks. The risk response plan should be reviewed and updated periodically throughout the project lifecycle, as new risks may emerge or existing risks may change. The risk owners are the persons assigned the responsibility of monitoring the risks and implementing the risk response actions. The risk owners should work with the risk manager and other stakeholders to evaluate the effectiveness of the risk response plan and make any necessary adjustments. In this case, the risk manager should ask the risk owners to review the risk response plan and see if there are any alternative or additional actions that can be taken to deal with the delay caused by the external team. Starting a quantitative analysis, crashing the schedule, or transferring the risk are not appropriate actions for this situation, as they are either too late, too costly, or too risky.Reference: = PMBOK Guide, 6th edition, pages 452-453; The Standard for Risk Management in Portfolios, Programs, and Projects, page 79.

A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?

A.

Execute the security risks contingency plan.

A.

Execute the security risks contingency plan.

Answers
B.

Get a report of customers affected by the risk.

B.

Get a report of customers affected by the risk.

Answers
C.

Identify residual and secondary risks.

C.

Identify residual and secondary risks.

Answers
D.

Coordinate a response with the risk owner.

D.

Coordinate a response with the risk owner.

Answers
Suggested answer: D

Explanation:

According to the PMBOK Guide, the risk owner is the person assigned the responsibility of monitoring the risk and implementing the risk response plan. The risk owner should be involved in the risk response execution and evaluation, and should communicate the results and outcomes to the relevant stakeholders. In the case of a data breach, the risk owner should coordinate a response with the risk manager and other parties involved, such as the security team, the legal team, the customer service team, and the senior management. The risk owner should also report the status of the risk and the effectiveness of the response plan to the risk manager. The risk manager should oversee the risk response process and ensure that the risk is handled appropriately and in alignment with the project objectives and stakeholder expectations.Reference: = PMBOK Guide, 6th edition, pages 452-453; The Standard for Risk Management in Portfolios, Programs, and Projects, page 79.

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.

What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?

A.

Reinforce to the stakeholders that the risk identification was done properly during the last sprint.

A.

Reinforce to the stakeholders that the risk identification was done properly during the last sprint.

Answers
B.

Highlight the importance of agreeing on the risk identification to avoid further delays.

B.

Highlight the importance of agreeing on the risk identification to avoid further delays.

Answers
C.

Conduct a separate meeting to show the risk identification analysis to the stakeholders.

C.

Conduct a separate meeting to show the risk identification analysis to the stakeholders.

Answers
D.

Ensure that the most knowledgeable members of the team validate risk identification processes.

D.

Ensure that the most knowledgeable members of the team validate risk identification processes.

Answers
Suggested answer: C

Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

A.

When the forecast activity date has been met or exceeded

A.

When the forecast activity date has been met or exceeded

Answers
B.

When the stakeholders agree a risk is no longer applicable

B.

When the stakeholders agree a risk is no longer applicable

Answers
C.

When the risk has been realized and can no longer happen again

C.

When the risk has been realized and can no longer happen again

Answers
D.

When iterative data analysis determines the risk is not applicable

D.

When iterative data analysis determines the risk is not applicable

Answers
Suggested answer: B

Explanation:

Project risks should be closed when the stakeholders agree a risk is no longer applicable. This ensures that risks are actively managed and only relevant risks are considered throughout the project lifecycle.

According to the PMI Risk Management Professional (PMI-RMP) Reference Materials, project risks are uncertain events or conditions that may have a positive or negative effect on one or more project objectives1. Project risks can be closed when they are no longer applicable to the project or its activities.The process of closing project risks involves verifying that the risk responses have been completed, documenting the outcomes, and evaluating the effectiveness of the risk management process2. The decision to close a project risk should be made by the stakeholders who are responsible for or affected by the risk, as they are the ones who can determine whether the risk is still relevant or not. Therefore, the correct answer is B. When the stakeholders agree a risk is no longer applicable.

The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

What is this an example of?

A.

Risk responses

A.

Risk responses

Answers
B.

Risk triggers

B.

Risk triggers

Answers
C.

Risk registers

C.

Risk registers

Answers
D.

Risk categories

D.

Risk categories

Answers
Suggested answer: B

Explanation:

The team is documenting all the checkpoints along the way that might indicate delays on critical deliverables, which is an example of risk triggers. Risk triggers are events or conditions that indicate a risk may be about to occur or has already occurred, helping the project team to monitor and respond to risks effectively.

Risk triggers are indicators or warning signs that a risk event is about to occur or has occurred. They help to monitor the status of risks and initiate risk responses when needed. Documenting risk triggers is part of the Plan Risk Responses process, which aims to develop options and actions to enhance opportunities and reduce threats to project objectives.Reference:The Standard for Risk Management in Portfolios, Programs, and Projects, page 78; PMBOK Guide, 6th edition, page 402.

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

A.

Risk analysis

A.

Risk analysis

Answers
B.

Risk identification

B.

Risk identification

Answers
C.

Risk treatment

C.

Risk treatment

Answers
D.

Risk evaluation

D.

Risk evaluation

Answers
Suggested answer: A

Explanation:

Risk impact assessment involves calculating the impact of identified risks. Risk analysis is the process of examining, estimating, and evaluating the impact of risks, which helps in calculating the impact (Reference: PMBOK Guide, 6th Edition, p. 417)

Risk analysis is the process of assessing the likelihood and impact of the identified risks on the program objectives. It helps to calculate the impact of the risks by using qualitative or quantitative methods. Risk analysis can provide useful information for risk prioritization, risk response planning, and risk reporting.Reference:PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 67; PMI, The Standard for Program Management, Fourth Edition, 2017, p. 113.

A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

What should the risk manager do next to visually organize the risks?

A.

Develop an affinity diagram

A.

Develop an affinity diagram

Answers
B.

Perform the analytical hierarchy process

B.

Perform the analytical hierarchy process

Answers
C.

Perform a SWOT analysis

C.

Perform a SWOT analysis

Answers
D.

Assign probability and impact

D.

Assign probability and impact

Answers
Suggested answer: A

Explanation:

An affinity diagram is a tool used to visually organize and group risks or ideas based on their similarities and categories. It helps in structuring the risks for further analysis and discussion. (Reference: PMBOK Guide, 6th Edition, p. 138)

According to the PMBOK Guide, anaffinity diagramis a tool and technique for the identify risks process that allows large numbers of ideas to be sorted into groups for review and analysis. An affinity diagram can help the risk manager to visually organize the risks identified in the pre-workshop survey by grouping them into categories based on their similarities or common characteristics. This can help the risk manager to facilitate the risk analysis and prioritization in the workshop, as well as to stimulate new patterns of thinking and generate additional risks.

Some of the other options are not relevant or appropriate for the question scenario:

Theanalytical hierarchy processis a technique for the plan risk management process that provides a method for comparing and ranking alternatives based on multiple criteria. It is not a tool for visually organizing risks.

ASWOT analysisis a technique for the identify risks process that examines the project from the perspective of its strengths, weaknesses, opportunities, and threats. It is not a tool for visually organizing risks, but rather for generating them.

Assigningprobability and impactis a technique for the perform qualitative risk analysis process that assesses the likelihood and the potential effect of each individual risk on the project objectives. It is not a tool for visually organizing risks, but rather for evaluating them.

Total 201 questions
Go to page: of 21