ExamGecko
Home / PMI / PMI-RMP / List of questions
Ask Question

PMI PMI-RMP Practice Test - Questions Answers, Page 10

Add to Whishlist

List of questions

Question 91

Report Export Collapse

While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

Become a Premium Member for full access
  Unlock Premium Member

Question 92

Report Export Collapse

When conducting a risk identification exercise, what two actions should the risk manager take? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 93

Report Export Collapse

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board's response?

Become a Premium Member for full access
  Unlock Premium Member

Question 94

Report Export Collapse

A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team's tasks have yet to be completed.

What should the risk manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 95

Report Export Collapse

A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 96

Report Export Collapse

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.

What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?

Become a Premium Member for full access
  Unlock Premium Member

Question 97

Report Export Collapse

Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Become a Premium Member for full access
  Unlock Premium Member

Question 98

Report Export Collapse

The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

What is this an example of?

Become a Premium Member for full access
  Unlock Premium Member

Question 99

Report Export Collapse

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

Become a Premium Member for full access
  Unlock Premium Member

Question 100

Report Export Collapse

A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

What should the risk manager do next to visually organize the risks?

Become a Premium Member for full access
  Unlock Premium Member
Total 273 questions
Go to page: of 28
Search

Related questions