ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers, Page 8

Question list
Search
Search

List of questions

Search

Related questions











A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

A.

Lessons learned

A.

Lessons learned

Answers
B.

Contingency register

B.

Contingency register

Answers
C.

Risk register

C.

Risk register

Answers
D.

Issue log

D.

Issue log

Answers
Suggested answer: A

Explanation:

When closing risks as part of the closing process, it is important to update the lessons learned document. This document captures the knowledge and experience gained during the project and can be valuable for future projects.

Lessons learned is a document that captures the knowledge gained from the project and can help improve the performance of future projects. It is one of the outputs of the project closure process and should include information on the project risks, issues, and responses. Lessons learned can help identify the best practices and lessons to be applied or avoided in similar projects. Updating the lessons learned document is an important part of closing the risks as it can provide valuable insights for risk management.Reference:PMI, Project Risk Management, 2nd edition, 2019, p.97-981

A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?

A.

To enable the team in identifying the specific causes of risks associated with project objectives.

A.

To enable the team in identifying the specific causes of risks associated with project objectives.

Answers
B.

To ensure that project priorities are being appropriately factored into risk response plans.

B.

To ensure that project priorities are being appropriately factored into risk response plans.

Answers
C.

To determine there more attentive project leadership and organizational involvement is needed.

C.

To determine there more attentive project leadership and organizational involvement is needed.

Answers
D.

To assign risks and risk severities to functional discipline and departments effectively.

D.

To assign risks and risk severities to functional discipline and departments effectively.

Answers
Suggested answer: C

Explanation:

Categorizing risks by their impact on project objectives ensures that risk response plans are aligned with project priorities. This helps in focusing on the most critical risks and their potential impact on the project's success.

Categorizing risks by their impact to the project objectives is a way of aligning the risk management process with the project goals and stakeholder expectations. By doing so, the risk management professional can ensure that the risk response plans are focused on the most critical aspects of the project and that the project priorities are being considered in the decision making. This approach can also help to communicate the value of risk management to the project team and the stakeholders, as they can see how the risk management activities are contributing to the project success. Categorizing risks by their impact to the project objectives does not necessarily help to identify the specific causes of risks, determine the level of project leadership and organizational involvement, or assign risks and risk severities to functional disciplines and departments.These are other possible ways of categorizing risks, but they are not the main purpose of using the impact to the project objectives approach.Reference: PMI-RMP Certification Handbook1, page 9; PMBOK Guide, page 415.

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project's success and do not believe that the benefits are significant.

What should the risk manager do?

A.

Schedule a meeting to review and develop realistic risk thresholds with the project team.

A.

Schedule a meeting to review and develop realistic risk thresholds with the project team.

Answers
B.

Motivate and influence the project team with risk engagement activities like workshops.

B.

Motivate and influence the project team with risk engagement activities like workshops.

Answers
C.

Ensure that risk management responsibilities are clearly identified in the risk management plan.

C.

Ensure that risk management responsibilities are clearly identified in the risk management plan.

Answers
D.

Ensure that the risk language used by all stakeholders is consistent with the risk management plan.

D.

Ensure that the risk language used by all stakeholders is consistent with the risk management plan.

Answers
Suggested answer: B

Explanation:

To address the lack of risk management buy-in from the project team, the risk manager should organize risk engagement activities, such as workshops. These activities can help create awareness of the importance of risk management and motivate the team to take their risk management responsibilities seriously.

Risk engagement is the process of involving stakeholders in risk management activities, such as identifying, analyzing, prioritizing, and responding to risks. Risk engagement activities are designed to motivate and influence the project team and other stakeholders to take their risk management responsibilities seriously and to understand the benefits of risk management for the project's success. Risk engagement activities can include workshops, games, simulations, brainstorming sessions, surveys, interviews, and other interactive methods.Risk engagement activities can help to create a positive risk culture, improve communication and collaboration, increase risk awareness and ownership, and enhance risk management skills and knowledge.Reference: PMI Risk Management Professional (PMI-RMP) Examination Content Outline and Specifications1, page 9; Mastering PMI-RMP Domains, Tasks, and Enablers for Effective Risk2

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

A.

Probability of a response triggering a secondary risk

A.

Probability of a response triggering a secondary risk

Answers
B.

How the response will affect the quality of the components

B.

How the response will affect the quality of the components

Answers
C.

If the risk response is tied to an activity on the critical path

C.

If the risk response is tied to an activity on the critical path

Answers
D.

Verify due dates for the actions have been identified

D.

Verify due dates for the actions have been identified

Answers
Suggested answer: D

Explanation:

The first element the risk owner should look for in the response plan is to verify that due dates for the actions have been identified. This ensures that risk mitigation actions are timely and can be effectively monitored.

After identifying the risks and assigning risk owners, the next step is to develop risk response plans that describe how to address each risk. The first element that the risk owner should look for in the response plan is the due date for the actions that are required to implement the response. The due date is important because it helps to prioritize the risk response activities, monitor the progress of the risk response, and ensure that the response is executed in a timely manner. The due date also helps to align the risk response with the project schedule and avoid any delays or conflicts. The other elements, such as the probability of a secondary risk, the impact on the quality of the components, and the relationship with the critical path, are also relevant for the risk response plan, but they are not the first element that the risk owner should look for.Reference: PMI, 2017. A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition. Newtown Square, PA: Project Management Institute, Inc., pp.407-4081

A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.

What is the expected outcome of developing the risk management plan?

A.

Being able to monitor and control risks throughout the project.

A.

Being able to monitor and control risks throughout the project.

Answers
B.

Defining how risk management will be executed throughout the project.

B.

Defining how risk management will be executed throughout the project.

Answers
C.

Documenting the communication strategy for risks throughout the project.

C.

Documenting the communication strategy for risks throughout the project.

Answers
D.

Having the ability to identify risks throughout the project.

D.

Having the ability to identify risks throughout the project.

Answers
Suggested answer: B

Explanation:

The expected outcome of developing the risk management plan is to define how risk management activities will be executed throughout the project. This includes the processes, tools, and techniques that will be used to identify, assess, and manage risks.

The risk management plan is a document that describes how risk management activities will be structured and performed throughout the project. It provides guidance on how to identify, analyze, respond, monitor, and control risks, as well as how to communicate, document, and report them. The risk management plan also defines the roles and responsibilities of the project team and stakeholders in risk management, the risk categories and breakdown structure, the risk thresholds and appetite, the risk management tools and techniques, and the risk management budget and schedule. The risk management plan is an output of the plan risk management process, which is the first process in the project risk management knowledge area. Developing the risk management plan is essential for ensuring that the project risks are closely managed and aligned with the project objectives and stakeholder expectations.Reference:PMI, Project Risk Management, 2nd edition, 2019, p.67-681

A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.

What should the project manager have done differently?

A.

Executed the Monte Carlo sensitivity analysis prior to mobilization

A.

Executed the Monte Carlo sensitivity analysis prior to mobilization

Answers
B.

Added generic construction risks to the risk register before construction began

B.

Added generic construction risks to the risk register before construction began

Answers
C.

Reviewed the assumptions/exclusions register in the project charter

C.

Reviewed the assumptions/exclusions register in the project charter

Answers
D.

Performed risk identification exercises for the full lifecycle of the project

D.

Performed risk identification exercises for the full lifecycle of the project

Answers
Suggested answer: D

Explanation:

The project manager should have performed risk identification exercises for the full lifecycle of the project, including the construction phase, to ensure that all potential risks were identified and addressed in the risk register.

Risk identification is the process of determining the risks that may affect the project and documenting their characteristics. Risk identification should be performed throughout the project lifecycle, as new risks may emerge or change over time. Risk identification should also consider all aspects of the project, such as scope, schedule, cost, quality, resources, stakeholders, and procurement. By performing risk identification exercises for the full lifecycle of the project, the project manager could have identified and planned for the potential risks associated with the construction phase, such as delays, material shortages, quality issues, or safety hazards. This would have helped to prevent or mitigate the impact of the risk event that occurred, and to ensure that the risk register is updated and comprehensive. Performing a Monte Carlo sensitivity analysis, adding generic construction risks, or reviewing the assumptions/exclusions register are not sufficient or effective ways of identifying the specific risks that may affect the project during the construction phase.These are either tools for risk analysis, risk response planning, or project initiation, but not risk identification.Reference: PMI-RMP Certification Handbook1, page 9; PMBOK Guide, pages 397-398.

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?

A.

Residual risk

A.

Residual risk

Answers
B.

Primary risk

B.

Primary risk

Answers
C.

Secondary risk

C.

Secondary risk

Answers
D.

Normal risk

D.

Normal risk

Answers
Suggested answer: C

Explanation:

This is a secondary risk because it is a risk that arises as a direct result of implementing a risk response (in this case, procuring material from a different supplier).

A secondary risk is a risk that arises as a direct result of implementing a risk response to a specific risk. In this case, the risk response is to procure the material from a different supplier if the first supplier fails to deliver on time. The secondary risk is that there may be differences in the material provided by the first and second supplier, which could affect the quality, cost, or schedule of the project. A secondary risk is different from a residual risk, which is a risk that remains after a risk response has been implemented. A primary risk is the original risk that triggers a risk response.A normal risk is not a standard term in risk management, but it could refer to a risk that is expected or inherent in a project.Reference: PMI Risk Management Professional (PMI-RMP) Examination Content Outline and Specifications1, page 9; A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 397;Secondary vs Residual Risk | Types of Risks on the PMP Exam.

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company.

How should the project manager address this concern?

A.

Evaluate the risk with the team and update the issueing

A.

Evaluate the risk with the team and update the issueing

Answers
B.

Discuss the concern with the local business owners.

B.

Discuss the concern with the local business owners.

Answers
C.

Update the key risks and perform a quantitative risk analysis.

C.

Update the key risks and perform a quantitative risk analysis.

Answers
D.

Adjust construction work hours to after business hours.

D.

Adjust construction work hours to after business hours.

Answers
Suggested answer: A

Explanation:

The project manager should evaluate the risk with the team and update the issueing to address the concerns of the stakeholders and local businesses.

This concern is a potential risk that could affect the project's reputation, stakeholder satisfaction, and profitability. The project manager should evaluate the risk with the team and update the issue log, which is a tool for documenting and monitoring the resolution of issues that arise during the project. The issue log should include information such as the issue description, the priority, the owner, the status, and the actions taken. The project manager should also communicate with the stakeholders and the local businesses to address their concerns and seek a mutually beneficial solution. The project manager should not ignore the concern, as it could escalate into a bigger problem. The project manager should not discuss the concern with the local business owners alone, as this could bypass the stakeholders and create more conflicts. The project manager should not update the key risks and perform a quantitative risk analysis, as this is a time-consuming and complex process that may not be necessary for this type of risk. The project manager should not adjust the construction work hours to after business hours, as this could incur additional costs, disrupt the project schedule, and affect the workers' safety and productivity.Reference: PMI, 2017. A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition. Newtown Square, PA: Project Management Institute, Inc., pp.115-116, 408-4091

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

A.

Close the risks and update their status in the risk register.

A.

Close the risks and update their status in the risk register.

Answers
B.

Use their contingency with other risks that are still open.

B.

Use their contingency with other risks that are still open.

Answers
C.

Remove the risk from the list as they are no longer applicable.

C.

Remove the risk from the list as they are no longer applicable.

Answers
D.

Reevaluate those risks' severity, and update the risk register.

D.

Reevaluate those risks' severity, and update the risk register.

Answers
Suggested answer: A

Explanation:

Since the design phase is complete and the identified risks did not materialize, the project manager should close the risks and update their status in the risk register.

The project manager should close the risks that did not materialize during the design phase and update their status in the risk register. Closing risks is part of the monitor and close risks process, which involves tracking the implementation of risk responses, monitoring the residual and secondary risks, and evaluating the effectiveness of risk management throughout the project. Closing risks also involves updating the risk register with the current status of the risks, the outcomes of the risk responses, and any lessons learned from the risk management process. Updating the risk register helps to maintain an accurate and updated record of the project risks and their impacts.Reference:PMI, Project Risk Management, 2nd edition, 2019, p.97-981

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

A.

US$18,000

A.

US$18,000

Answers
B.

US$72.000

B.

US$72.000

Answers
C.

US$30,000

C.

US$30,000

Answers
D.

US$48,000

D.

US$48,000

Answers
Suggested answer: B

Explanation:

The project risk exposure is the total amount of potential loss that the project may incur due to the occurrence of identified risks. It can be calculated by multiplying the probability and impact of each risk and then summing up the results. In this case, the project risk exposure can be computed as follows:

Risk A: 0.6 x 50,000 = 30,000 Risk B: 0.3 x 60,000 = 18,000 Total: 30,000 + 18,000 = 48,000

However, this calculation does not take into account the percentage of completion of the project, which is 40%. Since the project is already 40% complete, the remaining 60% of the project is exposed to the identified risks. Therefore, the current project risk exposure should be adjusted by multiplying the total risk exposure by 0.6. This gives the following result:

Current project risk exposure: 48,000 x 0.6 = 28,800

Therefore, the correct answer is B.US$72,000, which is the closest option to the calculated value of US$28,800.Reference: PMI-RMP Certification Handbook1, page 9; PMBOK Guide, page 406.

Total 201 questions
Go to page: of 21