ExamGecko
Home / PMI / PMI-RMP / List of questions
Ask Question

PMI PMI-RMP Practice Test - Questions Answers, Page 8

Add to Whishlist

List of questions

Question 71

Report Export Collapse

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Become a Premium Member for full access
  Unlock Premium Member

Question 72

Report Export Collapse

A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?

Become a Premium Member for full access
  Unlock Premium Member

Question 73

Report Export Collapse

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project's success and do not believe that the benefits are significant.

What should the risk manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 74

Report Export Collapse

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

Become a Premium Member for full access
  Unlock Premium Member

Question 75

Report Export Collapse

A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.

What is the expected outcome of developing the risk management plan?

Become a Premium Member for full access
  Unlock Premium Member

Question 76

Report Export Collapse

A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.

What should the project manager have done differently?

Become a Premium Member for full access
  Unlock Premium Member

Question 77

Report Export Collapse

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?

Become a Premium Member for full access
  Unlock Premium Member

Question 78

Report Export Collapse

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company.

How should the project manager address this concern?

Become a Premium Member for full access
  Unlock Premium Member

Question 79

Report Export Collapse

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 80

Report Export Collapse

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

Become a Premium Member for full access
  Unlock Premium Member
Total 273 questions
Go to page: of 28
Search

Related questions