PMI PMI-RMP Practice Test - Questions Answers, Page 8
List of questions
Related questions
A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.
Which document will need to be updated?
Lessons learned
Contingency register
Risk register
Issue log
A risk management professional is in the process of categorizing risks when a subject matter expert (SME) suggests categorizing the risks by their impact to the project objectives. Why should the risk management professional use this approach?
To enable the team in identifying the specific causes of risks associated with project objectives.
To ensure that project priorities are being appropriately factored into risk response plans.
To determine there more attentive project leadership and organizational involvement is needed.
To assign risks and risk severities to functional discipline and departments effectively.
Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project's success and do not believe that the benefits are significant.
What should the risk manager do?
Schedule a meeting to review and develop realistic risk thresholds with the project team.
Motivate and influence the project team with risk engagement activities like workshops.
Ensure that risk management responsibilities are clearly identified in the risk management plan.
Ensure that the risk language used by all stakeholders is consistent with the risk management plan.
After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?
Probability of a response triggering a secondary risk
How the response will affect the quality of the components
If the risk response is tied to an activity on the critical path
Verify due dates for the actions have been identified
A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.
What is the expected outcome of developing the risk management plan?
Being able to monitor and control risks throughout the project.
Defining how risk management will be executed throughout the project.
Documenting the communication strategy for risks throughout the project.
Having the ability to identify risks throughout the project.
A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.
What should the project manager have done differently?
Executed the Monte Carlo sensitivity analysis prior to mobilization
Added generic construction risks to the risk register before construction began
Reviewed the assumptions/exclusions register in the project charter
Performed risk identification exercises for the full lifecycle of the project
A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.
What type of risk is this?
Residual risk
Primary risk
Secondary risk
Normal risk
Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company.
How should the project manager address this concern?
Evaluate the risk with the team and update the issueing
Discuss the concern with the local business owners.
Update the key risks and perform a quantitative risk analysis.
Adjust construction work hours to after business hours.
A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.
What should the project manager do next?
Close the risks and update their status in the risk register.
Use their contingency with other risks that are still open.
Remove the risk from the list as they are no longer applicable.
Reevaluate those risks' severity, and update the risk register.
An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.
What is the current project risk exposure?
US$18,000
US$72.000
US$30,000
US$48,000
Question