PMI PMI-RMP Practice Test - Questions Answers, Page 9
List of questions
Related questions
The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.
How should this documentation be utilized in the future?
To return the remaining amount of the contingency reserve
To ensure information is recorded for lessons learned
To comply with the rules and regulations
To hold those who created the risk accountable
The project manager leading a company's digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.
What are two potential threats or opportunities under the SWOT analysis? (Choose two.)
The management team agreeing to include more resource for the digital signature initiative.
The organization's professional engineers having reservations about possible information tampering.
A growing number of competitors with digital signatures.
An elimination of manual steps associated with recording wet signatures
The growing adoption of mobile communications in the industry.
Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project's risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?
The risk management plan
The risk triggers
The risk prioritization criteria
The portfolio management plan
A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.
What should the risk manager do next to find out the correct limit?
Review the agreed-upon risk tolerance
Perform a sensitivity analysis of the risk
Find out the stakeholders' risk appetite
Use industry standard risk thresholds
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
Add contingencies to other tasks to mitigate similar risks.
Reassess risks with a new assumptions and constraints analysis.
Review the risk response plan looking for lessons learned.
Log the event in the issue log and update the project management plan.
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
Add contingencies to other tasks to mitigate similar risks.
Reassess risks with a new assumptions and constraints analysis.
Review the risk response plan looking for lessons learned.
Log the event in the issue log and update the project management plan.
The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?
Recommend the removal of risks to the project manager to reduce project risk exposure.
Advise the client that the project has exhausted contingency.
Quantify the risk exposure that exceeds project contingency.
Generate reports to assess and communicate the project risk level.
An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges.
What should the risk owner do?
Develop an efficient network protection solution quickly to mitigate the risk.
Escalate the case to the risk manager and wait for their instructions.
Conduct an analysis to determine the root cause of the failed response.
Apply a work around to eliminate or mitigate the impact of the threat.
A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.
What should the project risk manager monitor closely?
Risk thresholds
Risk response strategies
Risk management reports
Risk breakdown structure (RBS)
The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.
What are two options the risk manager should consult for the analysis? (Choose two.)
Proximity dales for open risks
Backlog of change orders to be submitted to client
Risks that have materialized and the overall risk profile
Number of schedule baseline changes approved
Risks due to the number of claims submitted to the client
Question