ExamGecko
Home Home / PMI / PMI-RMP

PMI PMI-RMP Practice Test - Questions Answers, Page 9

Question list
Search
Search

List of questions

Search

Related questions











The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.

How should this documentation be utilized in the future?

A.

To return the remaining amount of the contingency reserve

A.

To return the remaining amount of the contingency reserve

Answers
B.

To ensure information is recorded for lessons learned

B.

To ensure information is recorded for lessons learned

Answers
C.

To comply with the rules and regulations

C.

To comply with the rules and regulations

Answers
D.

To hold those who created the risk accountable

D.

To hold those who created the risk accountable

Answers
Suggested answer: B

Explanation:

Documenting the results of the risk monitoring and controlling process is important for creating lessons learned. This helps future projects by providing a reference for risk management practices and experiences.

The documentation of the results of monitoring and controlling risks is a valuable source of information for lessons learned. Lessons learned are the documented information that reflects both the positive and negative experiences of a project. They represent the organization's commitment to project management excellence and the project manager's opportunity to learn from the actual experiences of others. By documenting the results of monitoring and controlling risks, the project team can capture the effectiveness of the risk responses, the changes in the risk exposure, the root causes of the risks, the best practices and the lessons learned for future projects.This documentation can help to improve the risk management process, enhance the project performance, and increase the organizational knowledge base.Reference: PMI Risk Management Professional (PMI-RMP) Examination Content Outline and Specifications1, page 10; A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 406;Lessons learned - PMI.

The project manager leading a company's digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

What are two potential threats or opportunities under the SWOT analysis? (Choose two.)

A.

The management team agreeing to include more resource for the digital signature initiative.

A.

The management team agreeing to include more resource for the digital signature initiative.

Answers
B.

The organization's professional engineers having reservations about possible information tampering.

B.

The organization's professional engineers having reservations about possible information tampering.

Answers
C.

A growing number of competitors with digital signatures.

C.

A growing number of competitors with digital signatures.

Answers
D.

An elimination of manual steps associated with recording wet signatures

D.

An elimination of manual steps associated with recording wet signatures

Answers
E.

The growing adoption of mobile communications in the industry.

E.

The growing adoption of mobile communications in the industry.

Answers
Suggested answer: B, C

Explanation:

SWOT analysis identifies strengths, weaknesses, opportunities, and threats. In this case, B and C are potential threats or opportunities. B is a threat as engineers' reservations may hinder the initiative, and C is an opportunity as growing competition may drive the company to improve its digital signature capabilities.

A SWOT analysis is a technique used to identify the strengths, weaknesses, opportunities, and threats of a project, organization, or option. It helps to evaluate the internal and external factors that can affect the project's success or failure. In this question, the project manager has used a SWOT analysis to identify the threats and opportunities for the digital signature initiative. A threat is an external factor that can negatively impact the project's objectives, while an opportunity is an external factor that can positively impact the project's objectives. Therefore, two potential threats or opportunities under the SWOT analysis are:

B . The organization's professional engineers having reservations about possible information tampering. This is a threat because it can reduce the acceptance and adoption of the digital signature initiative by the key stakeholders, who are the professional engineers. They may have concerns about the security, reliability, and validity of the digital signatures, and may prefer to use the traditional wet signatures. This can affect the project's scope, quality, and stakeholder satisfaction.

C . A growing number of competitors with digital signatures. This is an opportunity because it can create a competitive advantage for the organization, as it can offer faster, cheaper, and more efficient services to its clients. The digital signature initiative can also help the organization to comply with the industry standards and regulations, and to enhance its reputation and brand image. This can affect the project's schedule, cost, and profitability.

The other options are not threats or opportunities under the SWOT analysis, because they are either internal factors or not relevant to the project's objectives. They are:

A . The management team agreeing to include more resource for the digital signature initiative. This is a strength, not a threat or an opportunity, because it is an internal factor that can help the project to achieve its objectives. It can provide more support, expertise, and funding for the project, and improve the project's performance and quality.

D . An elimination of manual steps associated with recording wet signatures. This is a benefit, not a threat or an opportunity, because it is an outcome or result of the project, not a factor that can affect the project. It can improve the efficiency, accuracy, and convenience of the project's deliverables, and reduce the errors, delays, and costs associated with the wet signatures.

E . The growing adoption of mobile communications in the industry. This is a trend, not a threat or an opportunity, because it is a general change or development in the industry, not a specific factor that can affect the project. It can influence the demand, expectations, and preferences of the project's customers and stakeholders, but it does not directly impact the project's objectives.

Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project's risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?

A.

The risk management plan

A.

The risk management plan

Answers
B.

The risk triggers

B.

The risk triggers

Answers
C.

The risk prioritization criteria

C.

The risk prioritization criteria

Answers
D.

The portfolio management plan

D.

The portfolio management plan

Answers
Suggested answer: A

Explanation:

The risk management plan provides guidance on how often the risk register should be updated or reviewed. It takes into account the specific industry, project, and organizational context, including the business rhythm.

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

A.

Review the agreed-upon risk tolerance

A.

Review the agreed-upon risk tolerance

Answers
B.

Perform a sensitivity analysis of the risk

B.

Perform a sensitivity analysis of the risk

Answers
C.

Find out the stakeholders' risk appetite

C.

Find out the stakeholders' risk appetite

Answers
D.

Use industry standard risk thresholds

D.

Use industry standard risk thresholds

Answers
Suggested answer: A

Explanation:

The risk manager should review the agreed-upon risk tolerance to determine the correct limit for continuing construction based on the chance of rain. Risk tolerance is the level of risk an organization is willing to accept and should be established during the risk management planning process.

Risk tolerance is the degree of uncertainty that a stakeholder is willing to accept in respect to a negative outcome on a project objective. Risk tolerance can be expressed as a percentage, a range, a value, or a qualitative statement. Risk tolerance should be agreed upon by the project team and the stakeholders at the beginning of the project, and documented in the risk management plan. The risk manager should review the agreed-upon risk tolerance to find out the correct limit for the rain probability that would affect the construction activity. This would help to resolve the conflicting opinions of the stakeholders and ensure that the risk management decisions are aligned with the project objectives and expectations. Reviewing the agreed-upon risk tolerance is the best option among the choices given, as it is the most relevant and reliable source of information for the risk manager.Performing a sensitivity analysis, finding out the stakeholders' risk appetite, or using industry standard risk thresholds are not as effective or appropriate ways of finding out the correct limit, as they do not reflect the specific agreement and context of the project.Reference: PMI-RMP Certification Handbook1, page 9; PMBOK Guide, pages 414-415.

A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?

A.

Add contingencies to other tasks to mitigate similar risks.

A.

Add contingencies to other tasks to mitigate similar risks.

Answers
B.

Reassess risks with a new assumptions and constraints analysis.

B.

Reassess risks with a new assumptions and constraints analysis.

Answers
C.

Review the risk response plan looking for lessons learned.

C.

Review the risk response plan looking for lessons learned.

Answers
D.

Log the event in the issue log and update the project management plan.

D.

Log the event in the issue log and update the project management plan.

Answers
Suggested answer: B

A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?

A.

Add contingencies to other tasks to mitigate similar risks.

A.

Add contingencies to other tasks to mitigate similar risks.

Answers
B.

Reassess risks with a new assumptions and constraints analysis.

B.

Reassess risks with a new assumptions and constraints analysis.

Answers
C.

Review the risk response plan looking for lessons learned.

C.

Review the risk response plan looking for lessons learned.

Answers
D.

Log the event in the issue log and update the project management plan.

D.

Log the event in the issue log and update the project management plan.

Answers
Suggested answer: B

Explanation:

The project manager should reassess risks by conducting a new assumptions and constraints analysis. This will help identify any previously overlooked risks and ensure that the risk register is comprehensive and up-to-date.

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.

Answers
B.

Advise the client that the project has exhausted contingency.

B.

Advise the client that the project has exhausted contingency.

Answers
C.

Quantify the risk exposure that exceeds project contingency.

C.

Quantify the risk exposure that exceeds project contingency.

Answers
D.

Generate reports to assess and communicate the project risk level.

D.

Generate reports to assess and communicate the project risk level.

Answers
Suggested answer: C

Explanation:

The project risk manager should generate reports to assess and communicate the project risk level to stakeholders. This helps in making informed decisions and taking appropriate actions to manage risks effectively.

The project risk manager should quantify the risk exposure that exceeds project contingency, as this will help to determine the amount of management reserve needed to cover the potential cost overruns or schedule delays. The project risk manager should also communicate this information to the project manager and other relevant stakeholders, and update the risk management plan accordingly.Reference:The Standard for Risk Management in Portfolios, Programs, and Projects, page 80; PMBOK Guide, 6th edition, page 407.

An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges.

What should the risk owner do?

A.

Develop an efficient network protection solution quickly to mitigate the risk.

A.

Develop an efficient network protection solution quickly to mitigate the risk.

Answers
B.

Escalate the case to the risk manager and wait for their instructions.

B.

Escalate the case to the risk manager and wait for their instructions.

Answers
C.

Conduct an analysis to determine the root cause of the failed response.

C.

Conduct an analysis to determine the root cause of the failed response.

Answers
D.

Apply a work around to eliminate or mitigate the impact of the threat.

D.

Apply a work around to eliminate or mitigate the impact of the threat.

Answers
Suggested answer: D

Explanation:

According to the PMBOK Guide, one of the tools and techniques for the implement risk responses process isroot cause analysis. Root cause analysis is a technique that focuses on identifying the fundamental reason for the occurrence of a problem or a risk. By conducting a root cause analysis, the risk owner can determine why the implemented measures were only partially successful and what caused the new unforeseen risk to emerge.This can help the risk owner to identify and implement more effective risk responses, as well as to update the risk register and the risk report with the new information1.Reference: PMBOK Guide, 6th edition, pages 452-453, 474-4751; PMI-RMP Exam Content Outline, 2015, page 8.

A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.

What should the project risk manager monitor closely?

A.

Risk thresholds

A.

Risk thresholds

Answers
B.

Risk response strategies

B.

Risk response strategies

Answers
C.

Risk management reports

C.

Risk management reports

Answers
D.

Risk breakdown structure (RBS)

D.

Risk breakdown structure (RBS)

Answers
Suggested answer: A

Explanation:

The project risk manager should monitor risk thresholds closely, as they represent the organization's risk appetite. In a project with a low risk appetite, it is essential to ensure that risks are managed within the defined thresholds to address stakeholders' concerns and maintain their confidence in the project's success.

According to the PMI Risk Management Professional (PMI-RMP) Reference Materials, risk thresholds are the measure of acceptable variation around an objective that reflects the risk appetite of the organization1.Risk appetite is the degree of uncertainty an entity is willing to take on in anticipation of a reward2. In this case, the project has a significant impact on the organization and the stakeholders have a low risk appetite, meaning they are not willing to accept much deviation from the project objectives. Therefore, the project risk manager should monitor the risk thresholds closely to ensure that the project risks do not exceed the acceptable level of variation and impact the project performance negatively. By monitoring the risk thresholds, the project risk manager can also identify when risk responses are needed and evaluate their effectiveness.

The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

A.

Proximity dales for open risks

A.

Proximity dales for open risks

Answers
B.

Backlog of change orders to be submitted to client

B.

Backlog of change orders to be submitted to client

Answers
C.

Risks that have materialized and the overall risk profile

C.

Risks that have materialized and the overall risk profile

Answers
D.

Number of schedule baseline changes approved

D.

Number of schedule baseline changes approved

Answers
E.

Risks due to the number of claims submitted to the client

E.

Risks due to the number of claims submitted to the client

Answers
Suggested answer: A, C

Explanation:

The risk manager should consult the risks that have materialized and the overall risk profile to analyze the performance of managing the risks, as well as the risks due to the number of claims submitted to the client. These options provide insights into how well risks are being managed and the potential impact on the project.

The risk manager should consult the risks that have materialized and the overall risk profile, as these are indicators of how well the risk management process is working and how the project is affected by the risks. The risk manager should also consult the risks due to the number of claims submitted to the client, as these are potential sources of conflict, litigation, and reputation damage that may impact the project objectives and stakeholder satisfaction.Reference:The Standard for Risk Management in Portfolios, Programs, and Projects, page 83; PMBOK Guide, 6th edition, page 414.

Total 201 questions
Go to page: of 21