ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 119 - PMI-ACP discussion

Report
Export

The project team is ahead of schedule and beginning to gold-plate the feature included in the current sprint. What should the agile project manager do?

A.
Since the team has extra time, notify the product owner and secure approval for the extra work on this feature.
Answers
A.
Since the team has extra time, notify the product owner and secure approval for the extra work on this feature.
B.
Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.
Answers
B.
Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.
C.
Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.
Answers
C.
Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.
D.
Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.
Answers
D.
Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.
Suggested answer: C
asked 23/09/2024
stefano atzei
33 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first