The project team is ahead of schedule and beginning to gold-plate the feature included in the current sprint. What should the agile project manager do?
A.
Since the team has extra time, notify the product owner and secure approval for the extra work on this feature.
B.
Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.
C.
Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.
D.
Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.