An angle team is working on a new product. To ensure that all unknown issues are clarified before committing to the scope, the team plans to work only on spike user stories for the next three sprints.

What should the agile coach do in this situation?

A.
Ensure that the spikes identify the risks early in the project to increase the chances of success
Answers
A.
Ensure that the spikes identify the risks early in the project to increase the chances of success
B.
Ensure that the business sponsor accepts the proposal and agrees 10 fund the additional spike sprints
Answers
B.
Ensure that the business sponsor accepts the proposal and agrees 10 fund the additional spike sprints
C.
Recommend that, in the first sprint user stones with higher priority be executed in addition to the spike
Answers
C.
Recommend that, in the first sprint user stones with higher priority be executed in addition to the spike
D.
Support the decision because release planning will be improved and the product backlog can be better groomed after ail spikes are executed
Answers
D.
Support the decision because release planning will be improved and the product backlog can be better groomed after ail spikes are executed
Suggested answer: D