Question 190 - PMI-ACP discussion
What should a learn do when they complete ail sprint goals earlier than expected?
A.
Begin working on an item in the backlog
B.
Ask the scrum master to select an item from the backlog on which to work
C.
Ask the product owner to select an item from the backlog on which to work
D.
Jointly decide with the scrum master on an item from the backlog on which to work