Universal Containers wants to track the time a Service Resource spends on each step of more complex repair jobs. This time could include travel, prep and on-site time.
How could the Service Resource's Time Sheet be
configured to track the total time spent on each step?
A, Relate the Time Sheet Entries to the Service Appointment.
A.
Relate the Time Sheet to the Service Appointment.
B.
Relate the Time Sheet to the Work Order Line Item.
C.
Relate the Time Sheet Entries to the Work Order Line Item.
Your answer: