CompTIA PK0-005 Practice Test - Questions Answers, Page 24
List of questions
Question 231
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?
Question 232
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Which of the following PRINCE2 processes includes creating the project plan?
Question 233
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?
Question 234
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?
Question 235
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?
Question 236
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?
Question 237
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?
Question 238
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A meeting agenda included the following items:
. Review the goals of the project.
. Review the progress of the project.
. Discuss if the project is ready to move forward.
Which of the following best describes this type of meeting?
Question 239
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?
Question 240
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?
Question