ExamGecko
Home / PMI / PgMP / List of questions
Ask Question

PMI PgMP Practice Test - Questions Answers, Page 41

Add to Whishlist

List of questions

Question 401

Report Export Collapse

An infrastructure program has 20 projects. The first half of these projects incurred multiple change orders and failed to be completed on time. The program manager meets with the project managers to discuss lessons learned and to understand the challenges. During the meeting, the project managers complain that key risks and a lack of resources resulted in missing deadlines.

What should the program manager do to ensure that the remaining 10 component projects stay on track?

Become a Premium Member for full access
  Unlock Premium Member

Question 402

Report Export Collapse

Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?

Become a Premium Member for full access
  Unlock Premium Member

Question 403

Report Export Collapse

A program with objectives that impact a large segment of the population receives negative commentary from organizations representing the public interest.

What action should the program manager take first?

Become a Premium Member for full access
  Unlock Premium Member

Question 404

Report Export Collapse

A program manager is leading a program to transform an organization's sales and customer service operations by introducing a new customer relationship management (CRM) solution. As the program progresses, the sponsor and other stakeholders are satisfied with the pace of the program's performance.

A stakeholder from the sales department now requests a new feature to integrate the CRM platform with another application. The program manager advises that this is out of scope, as it will require analysis and development and be a project on its own. The program manager then requests additional funding via the formal change management process and the new scope is approved.

What should the program manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 405

Report Export Collapse

A program has been established and preparation is complete.

Component projects are planned as a part of which of the following?

Become a Premium Member for full access
  Unlock Premium Member

Question 406

Report Export Collapse

A program manager is appointed to manage a new program. The organization's leadership has specified a list of benefits that the program should deliver and has requested that the program manager determine when incremental benefits can be realized.

What should the program manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 407

Report Export Collapse

A component is scheduled to close at the end of the week.

What should the program manager verify prior to allowing the component to close?

Become a Premium Member for full access
  Unlock Premium Member

Question 408

Report Export Collapse

The number of emerging risks increases in a component project and the program manager falls behind in reviewing and approving the plans. This impacts the component project manager's ability to effectively address the risks.

In this situation, what should the program manager change about the risk management plan?

Become a Premium Member for full access
  Unlock Premium Member

Question 409

Report Export Collapse

A municipal agency manages a city's water and wastewater infrastructure. Its six-year capital improvement program (CIP) is approximately US$4 billion, and is used for such things as improving aging infrastructure, addressing regulatory requirements, and upgrading facilities. The mayor and key stakeholders are concerned because of yearly rate increases for residents. After receiving proposals from program managers for this key program, which is half of the current

CIP, a program management team is hired and receives an approved business case.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 410

Report Export Collapse

A program manager assigns project managers to five component projects and continues to develop the program team.

Which of the following represents the program manager's strategy?

Become a Premium Member for full access
  Unlock Premium Member
Total 451 questions
Go to page: of 46
Search

Related questions