PMI PgMP Practice Test - Questions Answers, Page 44
List of questions
Related questions
A company is evaluating the implementation of enterprise resource planning (ERP) software. The program manager performs an analysis to confirm the program's feasibility.
What other important step should the program manager complete?
A new component project is approved by the program governance board. The funding for this component project will be provided by an organization different from the organization funding the program.
Would this be an acceptable funding arrangement?
One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set.
If the tolerance range is too narrow on a program, what effect will multiple minor changes have on the program?
The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required.
What should the program manager do next?
A large infrastructure development program involves three road construction projects, two sewage line construction projects, and one project to lay underground electric cables. During a program meeting, the project manager of a road construction project communicates that a project risk related to the interdependency with a sewage line project has crossed its risk threshold.
What should the program manager do next?
A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated, only 60 percent has been achieved.
What should the program manager do to ensure benefits realization?
A program manager is responsible for constructing a US$50 million building. Management suggests it will take three years to complete. The program manager can select a design-build option to optimize the construction schedule to 1.5 years. However, heavy demand for steel is causing price increases and delivery delays. If this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1.25 years.
What is the expected time of delivery?
A software deployment program for a multinational organization requires the engagement of subcontractors. During the program planning phase, the contracts manager informs the program manager that the primary subcontractor's agreement includes incentives that would potentially conflict with program objectives.
What should the program manager do first?
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.
How should the program manager demonstrate the program's progress?
Based on its board's mandate, an organization drafts a new business strategy to meet future challenges, put the business on track, and meet growth expectations. Key to this are upgrading the IT infrastructure and strategic direction to transition the computing platform from onsite to cloud-based, thereby optimizing costs, and providing scalability, performance and high availability.
How should the program manager use the program mission statement to engage program stakeholders?
Question