Question 1215 - PMP discussion
In an advanced stage of a project, a stakeholder who is not receiving the project status report communicates this to the project manager. After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.
What should the project manager do next?
Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder.
Ask the stakeholder to get the project status report from another stakeholder listed in the communications management plan.
Inform the project sponsor that there are stakeholders who are not included in the communications management plan.
Inform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan.