ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 6 - PMP discussion

Report
Export

A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope.

What should the project manager do?

A.
Discuss with the customer the risks identified and team's concerns
Answers
A.
Discuss with the customer the risks identified and team's concerns
B.
Discuss with the team, estimate the effort, and raise a change request
Answers
B.
Discuss with the team, estimate the effort, and raise a change request
C.
Ask the customer to go live and add the new functionality in the backlog
Answers
C.
Ask the customer to go live and add the new functionality in the backlog
D.
Ask the team to deliver the functionality on the agreed go-live date
Answers
D.
Ask the team to deliver the functionality on the agreed go-live date
Suggested answer: A
asked 23/09/2024
Anton Khodyakov
46 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first