A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the project?

A.

Confer with team members.

Answers
A.

Confer with team members.

B.

Discuss with the customer.

Answers
B.

Discuss with the customer.

C.

Review with security experts.

Answers
C.

Review with security experts.

D.

Schedule regular project audits.

Answers
D.

Schedule regular project audits.

Suggested answer: D