Due to a change in market conditions, the business value for the original project requirements has changed. What should the project manager consider for execution?

A.
Evaluate and work on small requirements to deliver business value.
Answers
A.
Evaluate and work on small requirements to deliver business value.
B.
Negotiate with the stakeholder to deliver with existing business value.
Answers
B.
Negotiate with the stakeholder to deliver with existing business value.
C.
Continue as planned since changes will have no impact on the project.
Answers
C.
Continue as planned since changes will have no impact on the project.
D.
Take into consideration the requirements with the modified business value.
Answers
D.
Take into consideration the requirements with the modified business value.
Suggested answer: D