A project team is prioritizing the creation of project artifacts and enforcing it rigidly, while they face issues with delays in deliverables. How should the project manager respond?
A.
Facilitate the implementation of an automated tool for the team to manage project artifacts.
B.
Implement stricter controls so that project artifact creation is given the utmost importance
C.
Recognize the team's efforts for documenting artifacts and motivate them with an incentive mechanism
D.
Advise the team that solely focusing on artifacts will not produce successful project deliverables