A project manager has heard about the large volume of emails the team receives each day, which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed.

To what type of communication is the team member referring?

A.

Pull communication

Answers
A.

Pull communication

B.

Mass communication

Answers
B.

Mass communication

C.

Interactive communication

Answers
C.

Interactive communication

D.

Push communication

Answers
D.

Push communication

Suggested answer: A

Explanation:

The team member is likely referring to accessing project-related information asynchronously, meaning they can access it at their convenience rather than relying on real-time communication like emails.