A team member who is working on a critical project deliverable reported that their computer is not working. The IT department says that due to a high workload, they will not be able to provide assistance for 1 week.

How should the project manager address this situation?

A.
Use project reserves to buy new equipment to avoid an impact to the critical path of the project
Answers
A.
Use project reserves to buy new equipment to avoid an impact to the critical path of the project
B.
Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer
Answers
B.
Schedule a meeting with the project sponsor to request a budget to buy or rent a new computer
C.
Explore options with the IT department to expedite the necessary repairs based on criticality of the project
Answers
C.
Explore options with the IT department to expedite the necessary repairs based on criticality of the project
D.
Ask the team member to find an innovative solution or workaround to overcome the issue and avoid project delays
Answers
D.
Ask the team member to find an innovative solution or workaround to overcome the issue and avoid project delays
Suggested answer: C