Question 2 - PMP discussion
Eight highly qualified experts have been assembled to work for a 6-month period on a specific aspect of an organization's product development process.
How should the project manager support this team to succeed?
A.
Define roles and targets for all team members and regularly follow up with one-to-one meetings to review progress.
B.
Hand over control of specific aspects of their roles as experts and let them agree on their own timelines and targets.
C.
Work with the team members to define the overall objective and support them to engage around the goal.
D.
Bring in a senior colleague who is also an expert to ensure the team is on track to achieve the goals and objectives.
Your answer: