A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager do to address this situation?

A.

Negotiate with the project sponsor immediately and establish a new project charter.

Answers
A.

Negotiate with the project sponsor immediately and establish a new project charter.

B.

Modify the project management plan and get approval from relevant stakeholders.

Answers
B.

Modify the project management plan and get approval from relevant stakeholders.

C.

Issue a change order to the change control board (CCB) and rebaseline the schedule.

Answers
C.

Issue a change order to the change control board (CCB) and rebaseline the schedule.

D.

Add more resources to recover the schedule without making changes to the baseline.

Answers
D.

Add more resources to recover the schedule without making changes to the baseline.

Suggested answer: B