An agile team has completed 9 out of 10 stories for the sprint. During the retrospective, a few team members pointed out that they finished all of their stories. However, one team member failed to finish a story.

What should the agile leader do?

A.

Emphasize to the team that each member is responsible for their story, but the team is collectively responsible for finishing the sprint.

Answers
A.

Emphasize to the team that each member is responsible for their story, but the team is collectively responsible for finishing the sprint.

B.

Suggest that the team assign stories at the beginning of the sprint based on each person's strengths to maximize performance.

Answers
B.

Suggest that the team assign stories at the beginning of the sprint based on each person's strengths to maximize performance.

C.

Work with the product owner to remove the story from the sprint because the points cannot be split.

Answers
C.

Work with the product owner to remove the story from the sprint because the points cannot be split.

D.

Ask the team to address this at the next sprint planning instead of at the retrospective.

Answers
D.

Ask the team to address this at the next sprint planning instead of at the retrospective.

Suggested answer: A