Question 101

Report Export Collapse

A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module. The marketing department believes that a main competitor is working on a similar product.

Which delivery approach should the project manager use for this project?

Extreme Programming (XP) delivery, to mitigate the high risk related to a new product
Extreme Programming (XP) delivery, to mitigate the high risk related to a new product
Traditional delivery, to ensure high quality and that the product meets market demands
Traditional delivery, to ensure high quality and that the product meets market demands
Incremental delivery, to ensure that mobile capability is released fast to the users
Incremental delivery, to ensure that mobile capability is released fast to the users
Iterative delivery, to ensure that user feedback is incorporated into the second iteration
Iterative delivery, to ensure that user feedback is incorporated into the second iteration
Suggested answer: C
asked 23/09/2024
Miguel Pinar Guruceta
49 questions

Question 102

Report Export Collapse

During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule.

What should the project manager do first?

Escalate to the management team for delay approval
Escalate to the management team for delay approval
Add the risk and the delay to the risk register
Add the risk and the delay to the risk register
Update the schedule to include the delay
Update the schedule to include the delay
Update the issue log and act to minimize the impact
Update the issue log and act to minimize the impact
Suggested answer: D
asked 23/09/2024
Elliott Leighton-Woodruff
37 questions

Question 103

Report Export Collapse

A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders. The local community is speculating the impact of the facility.

There are rumors of job opportunities and environmental impacts, which are listed on the project risk matrix.

What should the project manager do with regard to community engagement in this situation?

Build channels to extend communication efforts to the local community.
Build channels to extend communication efforts to the local community.
Focus on the sideward stakeholders only and let the organization manage the community.
Focus on the sideward stakeholders only and let the organization manage the community.
Use the city administration to address communication with the community.
Use the city administration to address communication with the community.
Include the local union representative in the high-power, high-impact stakeholder group.
Include the local union representative in the high-power, high-impact stakeholder group.
Suggested answer: A
asked 23/09/2024
Nick Wells
52 questions

Question 104

Report Export Collapse

A company that uses a predictive approach and operates in a highly regulated market is losing profitability because its product life cycle is taking longer than those of its competitors. A new project manager has been hired to change this scenario.

What approach should the project manager propose?

Migrate to an agile model, focusing primarily on an iterative approach, leaving the incremental life cycle as a next step
Migrate to an agile model, focusing primarily on an iterative approach, leaving the incremental life cycle as a next step
Change to an agile model, focusing primarily on the incremental life cycle, leaving the iterative approach as a next step
Change to an agile model, focusing primarily on the incremental life cycle, leaving the iterative approach as a next step
Maintain a predictive approach, but increase the focus on better planning and tracking to anticipate problems and avoid delays
Maintain a predictive approach, but increase the focus on better planning and tracking to anticipate problems and avoid delays
Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company's industry
Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company's industry
Suggested answer: D
asked 23/09/2024
Elyse Martinez
46 questions

Question 105

Report Export Collapse

A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before.

What should the project manager do?

Organize an early retrospective with the team to analyze the problem
Organize an early retrospective with the team to analyze the problem
Ask the product owner to write the specifications for the related user story
Ask the product owner to write the specifications for the related user story
Facilitate a problem-solving session with the team to analyze the problem
Facilitate a problem-solving session with the team to analyze the problem
Inform the project sponsor about the problem faced by the team
Inform the project sponsor about the problem faced by the team
Suggested answer: C
asked 23/09/2024
Ricardo Monsalve
40 questions

Question 106

Report Export Collapse

A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not shared properly among the team. This has caused delivery delays and, ultimately, the failure to complete the project.

What is the root cause of this issue?

Incorrect communication techniques applied during implementation
Incorrect communication techniques applied during implementation
Lack of team member training on documentation planning
Lack of team member training on documentation planning
Improper assignment of tasks to team member pairings
Improper assignment of tasks to team member pairings
Team cohesiveness was lost because team members worked in pairs
Team cohesiveness was lost because team members worked in pairs
Suggested answer: A
asked 23/09/2024
Serhan Azdiken
40 questions

Question 107

Report Export Collapse

A key stakeholder has recently started in a company and has been assigned to a hybrid project.

Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.

What should the project manager do?

Inform the project management office (PMO) that the team will use a predictive approach for this project
Inform the project management office (PMO) that the team will use a predictive approach for this project
Inform the stakeholder that they must level their knowledge with other stakeholders
Inform the stakeholder that they must level their knowledge with other stakeholders
Allocate time to mentor the stakeholder in the selected project approach
Allocate time to mentor the stakeholder in the selected project approach
Update the risk register with the potential impact and apprise the steering committee
Update the risk register with the potential impact and apprise the steering committee
Suggested answer: C
asked 23/09/2024
Gennaro Migliaccio
35 questions

Question 108

Report Export Collapse

A senior manager attends one of the project review meetings and expresses concern that the project will not meet the quality standards.

What should the project manager do?

Ask the senior manager to approve the user acceptance testing (UAT) plan
Ask the senior manager to approve the user acceptance testing (UAT) plan
Inform the senior manager that there are approved quality standards
Inform the senior manager that there are approved quality standards
Review the quality management plan with the senior manager
Review the quality management plan with the senior manager
Estimate the backlog items to forecast quality
Estimate the backlog items to forecast quality
Suggested answer: C
asked 23/09/2024
doaa elshazly
52 questions

Question 109

Report Export Collapse

Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.

How should the agile project leader resolve this situation?

Update the project budget with the released team members.
Update the project budget with the released team members.
Update the restriction log with the new team capacity.
Update the restriction log with the new team capacity.
Explain the new project requirements to the team.
Explain the new project requirements to the team.
Explain the new team velocity to the customer.
Explain the new team velocity to the customer.
Suggested answer: D
asked 23/09/2024
Glen Teis
44 questions

Question 110

Report Export Collapse

An IT project manager for a project that is 50% complete learns that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.

How should the project manager improve team dynamics?

Require that all team members be physically present for the weekly project review
Require that all team members be physically present for the weekly project review
Offer the team member an incentive to stay until the end of the project
Offer the team member an incentive to stay until the end of the project
Replace the team member with someone who has similar qualifications and is located closer
Replace the team member with someone who has similar qualifications and is located closer
Set up a weekly video conference to monitor the progress of the team member's work
Set up a weekly video conference to monitor the progress of the team member's work
Suggested answer: D
asked 23/09/2024
SAM E REYES
39 questions
Total 1.477 questions
Go to page: of 148