PMI PMP Practice Test - Questions Answers, Page 10
List of questions
Related questions
A global program is being kicked off, and various distributed teams are involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.
How should the project teams interact in their meetings?
A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team should handle.
What should the project manager do in this situation?
A company is transitioning projects from a predictive to an agile approach. The CFO is concerned that one of the agile projects has an important feature for the financial department that is being delayed for a later iteration.
What should the project manager do to clarify the situation?
A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings, the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.
How should the project manager ensure that project risks are reported accurately in the risk register?
A project manager recently finished a project and started managing a new project with a different supervisor. As part of the early project activities, the supervisor from the original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor.
What should the project manager do to resolve this conflict?
A project manager sent the first communication about the project management plan to the team.
The next day, two field engineers were asking about their roles and the project schedule.
What should the project manager have done?
A solution designer in an agile team often passes the design information to team members without any documentation. This has resulted in misunderstandings within the team.
What should the agile leader do?
A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.
Which evaluation practice should the project lead use to obtain accurate usage data?
A software project using an agile approach is facing quality issues with every release, generating many production problems.
What should the project manager do to fix the problem and improve the quality?
A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO) needs visibility of the regulatory constraints while maintaining a degree of flexibility.
Which tool can the project manager use?
Question