ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 12

List of questions

Question 111

Report Export Collapse

A product development team has team members located in four different countries. A senior manager is assigned the task of recruiting a project manager to manage this project and the virtual team.

Which skill is required for a project manager to successfully manage this team?

Possesses strong interpersonal skills to drive high-performing virtual teams
Possesses strong interpersonal skills to drive high-performing virtual teams
Plans and controls every aspect of the team's deliverables to avoid surprises
Plans and controls every aspect of the team's deliverables to avoid surprises
Speaks several languages and has lived in different countries
Speaks several languages and has lived in different countries
Implements the organization's standards and processes for the project
Implements the organization's standards and processes for the project
Suggested answer: A
asked 23/09/2024
Harshvir Bhati
40 questions

Question 112

Report Export Collapse

A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project time lines have slipped, and the staff is overwhelmed.

What should the project manager do to help the company meet their financial objectives?

Prioritize the projects, giving higher priority to projects that will increase profit
Prioritize the projects, giving higher priority to projects that will increase profit
Ensure that all of the projects are of high quality and are delivered on time
Ensure that all of the projects are of high quality and are delivered on time
Request that upper management hire additional staff to support the projects
Request that upper management hire additional staff to support the projects
Make sure the project is fast tracked so that slipped time lines are recovered
Make sure the project is fast tracked so that slipped time lines are recovered
Suggested answer: A
asked 23/09/2024
David Looby
39 questions

Question 113

Report Export Collapse

A project manager is assigned to a building construction project. The project manager has taken an agile course and wants to use agile practices in the project.

What should the project manager do?

Choose the agile practices that can be implemented in this type of construction project and apply them
Choose the agile practices that can be implemented in this type of construction project and apply them
Hire a consultant to provide a second opinion about whether agile can be applied to a construction project
Hire a consultant to provide a second opinion about whether agile can be applied to a construction project
Review the stages of the project to allocate additional budget for agile resources
Review the stages of the project to allocate additional budget for agile resources
Assign a scrum master to the project to implement agile practices in the project
Assign a scrum master to the project to implement agile practices in the project
Suggested answer: A
asked 23/09/2024
ALEXANDRE NGUYEN
40 questions

Question 114

Report Export Collapse

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating. As a result, lots of misunderstandings occurred.

What should the project manager do to address this issue?

Check the ground rules of the meeting to review the initial agreement with the team members
Check the ground rules of the meeting to review the initial agreement with the team members
Use round-robin check-ins to facilitate the meeting, so all participants have the opportunity to speak
Use round-robin check-ins to facilitate the meeting, so all participants have the opportunity to speak
Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates
Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates
Identify one team representative to speak up during the daily meeting and share the team updates
Identify one team representative to speak up during the daily meeting and share the team updates
Suggested answer: A
asked 23/09/2024
Rekik Tesfaye
41 questions

Question 115

Report Export Collapse

A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation.

What should the project manager have done to avoid this situation?

Established ground rules before the discussion had started
Established ground rules before the discussion had started
Reinforced that higher-level management has the decision power
Reinforced that higher-level management has the decision power
Invited a high-level sponsor to the meeting to reduce the level of disagreement
Invited a high-level sponsor to the meeting to reduce the level of disagreement
Asked stakeholders not to voice their opinions during the meeting
Asked stakeholders not to voice their opinions during the meeting
Suggested answer: A
asked 23/09/2024
Sergio Guerra
46 questions

Question 116

Report Export Collapse

While monitoring a project at a work site, the project manager notices that the site team's work breaks have increased by a few minutes every week.

How should the project manager approach this?

Dismiss some of the workers for failing to adhere to the break policy
Dismiss some of the workers for failing to adhere to the break policy
Issue a formal written warning to all hourly workers for their break tardiness
Issue a formal written warning to all hourly workers for their break tardiness
Have a meeting with the team to discuss the issue and propose solutions
Have a meeting with the team to discuss the issue and propose solutions
Reduce payment to the workers due to their extended breaks
Reduce payment to the workers due to their extended breaks
Suggested answer: C
asked 23/09/2024
Carlos Cabezas
53 questions

Question 117

Report Export Collapse

A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.

How will the project manager be able to complete this task?

Call a meeting with the project team to identify the most appropriate approach
Call a meeting with the project team to identify the most appropriate approach
Tell the owner that a rough order of magnitude will be provided
Tell the owner that a rough order of magnitude will be provided
Contact a subject matter expert (SME) for advice and consultation
Contact a subject matter expert (SME) for advice and consultation
Tell the owner that the task requires more time and expertise
Tell the owner that the task requires more time and expertise
Suggested answer: B
asked 23/09/2024
Keenan Bragg
45 questions

Question 118

Report Export Collapse

A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office (PMO) recommends the project manager to lead the next similar project.

What should the project manager do next?

Engage key stakeholders to complete and deliver lessons learned.
Engage key stakeholders to complete and deliver lessons learned.
Select the same stakeholders for the next project to avoid doing knowledge transfer.
Select the same stakeholders for the next project to avoid doing knowledge transfer.
Present the project achievements and delegate knowledge transfer to the steering committee.
Present the project achievements and delegate knowledge transfer to the steering committee.
Request the PMO to manage the lessons learned repository.
Request the PMO to manage the lessons learned repository.
Suggested answer: A
asked 23/09/2024
Bartosz Szewczyk
40 questions

Question 119

Report Export Collapse

In order to increase a project's profit margin, the project manager and subject matter experts (SMEs) agreed to select the oldest model of a specific machine available in the market. When the machine reached its destination country, it was blocked by customs authorities who restricted the import of this machine model.

What should the project manager have done to prevent this from happening?

Ensured that the SMEs correctly defined the project scope and the machine model.
Ensured that the SMEs correctly defined the project scope and the machine model.
Ensured the project sponsor provided enough funding to purchase the latest version of the machine.
Ensured the project sponsor provided enough funding to purchase the latest version of the machine.
Ensured that regulatory compliance was considered in the quality management plan.
Ensured that regulatory compliance was considered in the quality management plan.
Ensured that the technical team researched and selected the latest model of the machine.
Ensured that the technical team researched and selected the latest model of the machine.
Suggested answer: C
asked 23/09/2024
Vidana Weerasinghe
49 questions

Question 120

Report Export Collapse

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?

Defined the skill requirements more clearly in the scope statement.
Defined the skill requirements more clearly in the scope statement.
Asked the manager to follow the agreed-upon resource management plan.
Asked the manager to follow the agreed-upon resource management plan.
Conducted periodic reviews with the manager on resource availability.
Conducted periodic reviews with the manager on resource availability.
Consulted with the installation team on a regular basis to check for conflicts.
Consulted with the installation team on a regular basis to check for conflicts.
Suggested answer: C
asked 23/09/2024
Mr Fraser Watson
38 questions
Total 1.477 questions
Go to page: of 148
Search

Related questions