ExamGecko
Home Home / PMI / PMP

PMI PMP Practice Test - Questions Answers, Page 120

Question list
Search
Search

List of questions

Search

Related questions











The sponsor of a newly formed agile project is struggling to understand the scope and to determine when critical product features will be ready to use. What should the project manager do?

A.
Move the team's kanban board to a more visible place to improve the communication with key stakeholders.
A.
Move the team's kanban board to a more visible place to improve the communication with key stakeholders.
Answers
B.
Create a detailed project management plan with all planned releases and the tasks needed to deliver them.
B.
Create a detailed project management plan with all planned releases and the tasks needed to deliver them.
Answers
C.
Establish the project vision, break down the mam features backlog, prioritize, and create an overall release plan.
C.
Establish the project vision, break down the mam features backlog, prioritize, and create an overall release plan.
Answers
D.
Invite the stakeholder to the project's daily meetings, providing better visibility on what the team is working on.
D.
Invite the stakeholder to the project's daily meetings, providing better visibility on what the team is working on.
Answers
Suggested answer: C

A risk was raised during the initiation of a project. The supplier discontinued software support for one of the project's required inputs. The project manager planned a reserve budget to allow the project to continue in the event of this occurrence.

What should the project manager do?

A.
Tell the project team to stop work, as software support will be canceled and the project cannot continue.
A.
Tell the project team to stop work, as software support will be canceled and the project cannot continue.
Answers
B.
Advise the supplier that the sponsor will pay for software support as previously planned.
B.
Advise the supplier that the sponsor will pay for software support as previously planned.
Answers
C.
Ask the supplier to continue providing software support until the end of the project.
C.
Ask the supplier to continue providing software support until the end of the project.
Answers
D.
Inform the sponsor that the risk has been realized and that a decision has to be made for the project to continue.
D.
Inform the sponsor that the risk has been realized and that a decision has to be made for the project to continue.
Answers
Suggested answer: D

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

A.
Delegate certain authorities and share information to allow fair decision-making.
A.
Delegate certain authorities and share information to allow fair decision-making.
Answers
B.
Delegate most authorities and share information to allow fair decision-making.
B.
Delegate most authorities and share information to allow fair decision-making.
Answers
C.
Delegate most authorities and control the authority by withholding important information.
C.
Delegate most authorities and control the authority by withholding important information.
Answers
D.
Delegate certain authorities and control the authority by withholding important information.
D.
Delegate certain authorities and control the authority by withholding important information.
Answers
Suggested answer: A

For some time now, doubts have been raised about who is responsible for delivering a key benefit of a project. What should the project manager do next?

A.
Meet with the stakeholders involved to clearly define their roles and responsibilities with regard to the benefit.
A.
Meet with the stakeholders involved to clearly define their roles and responsibilities with regard to the benefit.
Answers
B.
Understand the context of the situation and escalate the problem to the steering committee.
B.
Understand the context of the situation and escalate the problem to the steering committee.
Answers
C.
Document the risk in the risk register and generate the risk responses and their respective associated plans.
C.
Document the risk in the risk register and generate the risk responses and their respective associated plans.
Answers
D.
Meet with the customer to obtain consensus with the recipient of the benefit and determine a means to deliver the benefit.
D.
Meet with the customer to obtain consensus with the recipient of the benefit and determine a means to deliver the benefit.
Answers
Suggested answer: A

A project manager is assigned to a new project. The project management office (PMO) and the project manager agree that this is the night opportunity to include daily standup meetings. The project team has never used such tools, and a few members are challenging the decision.

What should the project manager do in this situation?

A.
Update the project schedule to consider a daily standup as part of the project design phase
A.
Update the project schedule to consider a daily standup as part of the project design phase
Answers
B.
Engage an external vendor to perform the design phase under an iterative approach
B.
Engage an external vendor to perform the design phase under an iterative approach
Answers
C.
Request that new team members familiar with iterative approaches be assigned to this project
C.
Request that new team members familiar with iterative approaches be assigned to this project
Answers
D.
Define the ground rules, responsibilities, and conflict management strategies
D.
Define the ground rules, responsibilities, and conflict management strategies
Answers
Suggested answer: D

A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.

How should the project manager proceed?

A.
Perform a gap analysis on renting in each of the locations.
A.
Perform a gap analysis on renting in each of the locations.
Answers
B.
Calculate the costs for each option in each location and compare the net present value (NPV) for each.
B.
Calculate the costs for each option in each location and compare the net present value (NPV) for each.
Answers
C.
Perform a Kano analysis on building a new branch versus renting in each of the locations.
C.
Perform a Kano analysis on building a new branch versus renting in each of the locations.
Answers
D.
Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.
D.
Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.
Answers
Suggested answer: B

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee:

Actual progress = 2 units

Planned progress = 3 units

Actual cost (AC) = 2 units

Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

A.
The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted
A.
The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted
Answers
B.
The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken
B.
The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken
Answers
C.
The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities
C.
The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities
Answers
D.
The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings
D.
The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings
Answers
Suggested answer: C

A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.

What should have been done to avoid this problem?

A.
Utilized three-point estimates
A.
Utilized three-point estimates
Answers
B.
Validated the schedule performance index (SPI) to evaluate deviation
B.
Validated the schedule performance index (SPI) to evaluate deviation
Answers
C.
Included lessons learned from past projects
C.
Included lessons learned from past projects
Answers
D.
Used bottom-up estimating
D.
Used bottom-up estimating
Answers
Suggested answer: D

A project manager manages multiple information technology (IT) projects in a matrix organization.

The project manager schedules a meeting with one of the functional managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

A.
Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software
A.
Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software
Answers
B.
Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software
B.
Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software
Answers
C.
Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained
C.
Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained
Answers
D.
Request a meeting with the sponsor to change the scope to allow the development team to conduct testing
D.
Request a meeting with the sponsor to change the scope to allow the development team to conduct testing
Answers
Suggested answer: C

A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner's statement?

A.
The product owner trusts the team and is marking the product as complete.
A.
The product owner trusts the team and is marking the product as complete.
Answers
B.
The product owner does not have visibility into what the team has done in the product increment.
B.
The product owner does not have visibility into what the team has done in the product increment.
Answers
C.
The product owner will release the product to customers without showing them a demo.
C.
The product owner will release the product to customers without showing them a demo.
Answers
D.
The product owner has evaluated the product against the definition of done (DoD).
D.
The product owner has evaluated the product against the definition of done (DoD).
Answers
Suggested answer: D
Total 1.477 questions
Go to page: of 148