Question 1460 - PMP discussion

Report
Export

In a project, one core team member tends to do all the work and ensures all tasks are completed.

This core team member is soon leaving the project, which may make the project vulnerable.

What should the project manager do?

A.

Ensure the activities of this team member are distributed across the project team.

Answers
A.

Ensure the activities of this team member are distributed across the project team.

B.

Assess a mechanism for knowledge transfer among the team members.

Answers
B.

Assess a mechanism for knowledge transfer among the team members.

C.

Ask human resources (HR) to counsel the team member to balance the workload.

Answers
C.

Ask human resources (HR) to counsel the team member to balance the workload.

D.

Motivate the team member to stay by providing them with incentives.

Answers
D.

Motivate the team member to stay by providing them with incentives.

Suggested answer: B
asked 12/11/2024
Steve Jenkins-Thorkildson
39 questions
User
Your answer:
0 comments