A project manager for a construction site realizes the importance of stakeholder relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

A.

Assess the need to collaborate with the community.

Answers
A.

Assess the need to collaborate with the community.

B.

Analyze the need to negotiate with the community.

Answers
B.

Analyze the need to negotiate with the community.

C.

Assess the information requirements of the community.

Answers
C.

Assess the information requirements of the community.

D.

Analyze stakeholder diversity in the community.

Answers
D.

Analyze stakeholder diversity in the community.

Suggested answer: C