A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.

What should the project manager use to explain the project scope?

A.

User stories

Answers
A.

User stories

B.

Product backlog

Answers
B.

Product backlog

C.

Product roadmap

Answers
C.

Product roadmap

D.

Business requirements document

Answers
D.

Business requirements document

Suggested answer: B