While finalizing project management plans, a customer provides the project manager with a new set of quality standards to which the final product must adhere.
What should the project manager do to ensure a smooth delivery of the product?
A.
Involve the client in risk identification
B.
Agree with the client on a new project charter
C.
Involve the client in a performance gap analysis
D.
Agree with the client on acceptance criteria