While finalizing project management plans, a customer provides the project manager with a new set of quality standards to which the final product must adhere.

What should the project manager do to ensure a smooth delivery of the product?

A.
Involve the client in risk identification
Answers
A.
Involve the client in risk identification
B.
Agree with the client on a new project charter
Answers
B.
Agree with the client on a new project charter
C.
Involve the client in a performance gap analysis
Answers
C.
Involve the client in a performance gap analysis
D.
Agree with the client on acceptance criteria
Answers
D.
Agree with the client on acceptance criteria
Suggested answer: C