Question 31 - PMP discussion
A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path.
What should the project manager do?
A.
Report the delay with rectifying actions to the project management office (PMO).
B.
Rebaseline the project schedule to absorb the delay.
C.
Notify the project steering committee about the cause of the delay.
D.
Report the delay with rectifying actions to the change control board (CCB) for review.