Question 30 - PMP discussion
In a newly formed project team, one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team.
What should the project manager do?
A.
Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges
B.
Set up team-building activities with the project team members to reduce tension
C.
Ask the team member to enter this potential schedule delay in the risk register
D.
Actively listen to the team member and identify ways to support their needs in completing the tasks