A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.

What should the project manager have done to avoid this issue?

A.
The customer's requirements should have been captured and modified to meet the supplier's standards.
Answers
A.
The customer's requirements should have been captured and modified to meet the supplier's standards.
B.
The iteration review planning meeting should have been planned accordingly.
Answers
B.
The iteration review planning meeting should have been planned accordingly.
C.
The customer's requirements should have been captured in order to meet the customer's standards.
Answers
C.
The customer's requirements should have been captured in order to meet the customer's standards.
D.
The sprint retrospective meeting should have included necessary stakeholders.
Answers
D.
The sprint retrospective meeting should have included necessary stakeholders.
Suggested answer: C