Question 1329 - PMP discussion
A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.
What should the project manager do next?
A.
Perform stakeholder engagement.
B.
Perform integrated change control.
C.
Update the quality management plan.
D.
Update the risk management plan.
Your answer: