Question 1204 - PMP discussion
A key business stakeholder sent emails to the developers with complaints based on the last few sprints. The developers forwarded the emails to the project manager but have not yet responded to the stakeholder.
What should the project manager recommend to the developers?
A.
Analyze and perform a root cause analysis (RCA).
B.
Add the situation to the issue log.
C.
Forward the emails to the product owner.
D.
Set up a team meeting to discuss a response.