ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1205 - PMP discussion

Report
Export

An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project. The team estimates the risk level as low.

What should the project manager do?

A.

Create a risk register to identify, capture, review, and manage risks using a risk management process.

Answers
A.

Create a risk register to identify, capture, review, and manage risks using a risk management process.

B.

Trust the development team's risk estimation and inform the project sponsor that the risks will be evaluated at a later time.

Answers
B.

Trust the development team's risk estimation and inform the project sponsor that the risks will be evaluated at a later time.

C.

Create a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.

Answers
C.

Create a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.

D.

Capture all the backlog entries assessed by the development team to have evidence that risk management has been completed.

Answers
D.

Capture all the backlog entries assessed by the development team to have evidence that risk management has been completed.

Suggested answer: A
asked 12/11/2024
Dan Yann
47 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first