A supplier that the company has used for years has trouble accepting the new terms of an agile contract. They do not understand the terms in the contract and feel they should not have to sign it because they have had a long relationship with the company.
Which action should the project manager take?
A.
Train the supplier in agile approaches to help them understand the contract.
B.
Change contract terms and conditions to avoid losing the supplier.
C.
Issue a request for proposal (RFP) to find new suppliers with agile experience.
D.
Ask the team if they can do the work until there is an available supplier.